Fuchs Lubricants development project, South Africa – update


Image by Tasneem Bulbulia
Name of the Project
Fuchs Lubricants development project.
Location
Isando, Johannesburg, in Gauteng, South Africa.
Project Owner/s
Independent lubricant manufacturer Fuchs Lubricants South Africa, a subsidiary of Fuchs Petrolub.
Project Description
The Phase 1 involved the construction of a new office complex and new warehouse.
The office block comprises three floors with different department divisions, so-called hot seats for external sales representatives, several meeting areas, boardrooms, a multipurpose medical room, a canteen with indoor and outdoor seating, coffee and tea stations, as well as a rooftop entertainment area.
There is scope to increase the size of the office in the future, if required.
The new warehouse system will provide much-needed storage space and modernisation of systems, and enhance efficiencies for the company.
Phase 2 will comprise a new lubricants plant to bolster the company’s strong growth and expansion plans for the continent.
Potential Job Creation
Not stated.
Capital Expenditure
Phase 1 of the project will require an investment of about R250-million.
Phase 2 will cost about R500-million.
Planned Start/End Date
The warehouse construction took 15 months, starting in March 2021, while the office construction was an 11-month project, starting in June 2021. Fuchs officially launched its newly built head office and warehouse on May 13.
Latest Developments
Phase 1 of the project has been completed on time and within budget.
Construction of Phase 2 is under way, with design and conceptualisation completed and construction to begin in stages.
"We envisage to complete our investment in Phase 2 over the next five to ten years as economic conditions permit," MD Paul Deppe has indicated.
Key Contracts, Suppliers and Consultants
DRA Global (engineering, procurement and construction management); Industrial Logistic Systems (warehouse consultant); and ICM Architectural Studio (architect).
Contact Details for Project Information
Fuchs Lubricants South Africa, tel +27 11 565 9600.
NGAGE senior account executive Rachel Mekgwe, on behalf of Fuchs Lubricants South Africa, tel +27 11 867 7763 or email rachel@ngage.co.za.