Kamoa-Kakula copper project, Democratic Republic of Congo – update
Photo by Ivanhoe Mines
Name of the Project
Kamoa-Kakula copper project.
Location
The Kolwezi district of Lualaba province, in the Democratic Republic of Congo (DRC).
Project Owner/s
Kamoa Copper, a joint venture (JV) between base and precious metals developer Ivanhoe Mines, with 39.6% ownership; Zijin Mining Group, with 39.6% ownership; Crystal River Global, with 0.8% ownership; and the DRC government, with 20% ownership.
Project Description
Ivanhoe Mines has announced outstanding economic results in the independent integrated development plan for the tier-one Kamoa-Kakula copper project.
The Kamoa-Kakula Integrated Development Plan 2020 comprises three development scenarios: the Kakula definitive feasibility study (DFS), the Kakula-Kansoko prefeasibility study (PFS) and the Kamoa-Kakula preliminary economic assessment (PEA).
Kakula
The Kakula DFS proposes the development of a Stage 1, six-million-tonne-a-year underground mine and surface processing complex at the Kakula deposit, with a capacity of 7.6-million tonnes a year built in two modules of 3.8-million tonnes a year. For this option, 110-million tonnes will be mined at an average grade of 5.22% copper, producing 8.5-million tonnes of high-grade copper concentrate and containing about 10.8-billion pounds of copper.
Kakula-Kansoko
The Kakula-Kansoko 2020 PFS evaluates the development of mining activities at the Kansoko deposit in addition to the Kakula mine, initially at a rate of 1.6-million tonnes a year, to supply the concentrator at Kakula, eventually ramping up to six-million tonnes a year as the reserves at Kakula are depleted.
Kamoa-Kakula
The Kamoa-Kakula 2020 PEA assesses an additional development option of mining several deposits on the Kamoa-Kakula project as an integrated, 19-million-tonne-a-year mining, processing and smelting complex, built in multiple stages.
An initial six-million-tonne-a-year mining operation will be established at the Kakula mine on the Kakula deposit, which will be followed by a separate six-million-tonne-a-year mining operation at the Kansoko mine. A third six-million-tonne-a-year mine will then be established at the Kakula West mine, in addition to a fourth initial mine in the Kamoa North area operating at one-million tonnes a year. The processing plant will be built in five modules of 3.8-million tonnes a year, with an ultimate capacity of one-million tonnes a year.
As the resources at the Kakula, Kansoko and Kakula West mines are mined out, production will begin sequentially at five other mines in the Kamoa North area to maintain throughput of 19-million tonnes a year to the existing concentrator and smelter complex.
Each mining operation is expected to be a separate underground mine, with a shared processing facility and surface infrastructure located at Kakula. Material will be transported to the Kakula processing complex using a system of overland conveyors. Included in this scenario is the construction of a direct-to-blister copper smelter with a capacity of one-million tonnes of copper concentrate a year.
Potential Job Creation
Once the two processing plants at Kakula are operating, Ivanhoe expects to employ almost 2 000 permanent Kamoa employees.
Net Present Value/Internal Rate of Return
The Kakula DFS yields an after-tax net present value (NPV), at an 8% discount rate, of $5.5-billion and an internal rate of return (IRR) of 77% over a 21-year mine life, with a payback of 2.3 years.
The Kakula-Kansoko PFS yields an after-tax NPV, at an 8% discount rate, of $6.6-billion and an IRR of 69% over a 37-year mine life, with a payback of 2.5 years.
The Kamoa-Kakula PEA yields a potential after-tax NPV, at an 8% discount rate, of $11.1-billion and an IRR of 56% over a mine life of more than 40 years, with a payback of 3.6 years.
Capital Expenditure
The Kakula DFS estimates peak funding at $775-million, remaining initial capital costs at $646-million and expansion capital costs at $594-million.
The Kakula-Kansoko PFS estimates peak funding at $848-million, remaining initial capital costs at $695-million and expansion capital costs at $750-million.
The Kamoa-Kakula PEA estimates peak funding at $784-million, remaining initial capital costs at $715-million and expansion capital costs at $4.46-billion.
Planned Start/End Date
The initial production of copper concentrate at the Kakula mine processing plant began on May 25, 2021, and achieved commercial production on July 1, 2021.
The expansion of the Kakula processing plant will be brought forward from the first quarter of 2023 to the third quarter of 2022.
Latest Developments
Ivanhoe Mines has reported that the 3.8-million-tonne-a-year Phase 2 concentrator plant is expected to be 93% complete by January 31, with hot commissioning of the concentrator on track to start in April.
Ivanhoe co-chairpersons Robert Friedland and Yufeng “Miles” Sun have noted that this schedule is at the front end of its previous guidance of the second quarter, as well as several months ahead of the original schedule.
Hot commissioning involves introducing first ore into the plant at a reduced feed rate to set equipment parameters and test performance, with the feed rate being subsequently steadily increased.
The first copper concentrate produced from the Phase 2 plant is expected about one week after ore is fed into the ball mills.
The Phase 2 plant is identical to the 3.8-million-tonne-a-year Phase 1 concentrator plant and, as a result, a faster ramp-up profile is expected, with the added benefit of operational knowledge gained during the commissioning of Phase 1.
Ivanhoe has reported that the Phase 1 concentrator reached monthly design throughput during September 2021, which was the fourth full month of operation. First ore was introduced into Kamoa Copper’s Phase 1 concentrator plant on May 20, 2021, and first concentrate was produced from the Phase 1 plant on May 25.
The Phase 1 concentrator is operating at a higher throughput than its design capacity, by more than 15%, with 117% of design throughput achieved in December.
Copper recoveries also are being achieved that are more than design recovery of 86%, depending on feed grade, with December’s recoveries about 2% higher.
Going forward, a dedicated project team has been appointed to debottleneck the Phase 1 and Phase 2 concentrators after the latter’s commissioning, with targeted improvements aimed at increasing plant throughput from the design of 7.6-million tonnes a year to nine-million tonnes a year – producing up to 450 000 t/y of copper in concentrate from the first two plants once steady-state is achieved.
Production guidance for the Kamoa-Kakula copper complex has been estimated at between 290 000 t and 340 000 t of copper in concentrate.
Ivanhoe has reported that the Phase 3 expansion of Kamoa-Kakula, which is expected to be commissioned in the fourth quarter of 2024, is also advancing, with work ongoing on a new boxcut to access the Kamoa mine.
In this regard, an updated prefeasibility study, including the Phase 3 expansion, is expected in the third quarter of this year.
Key Contracts, Suppliers and Consultants
DFS/PFS/PEA:
OreWin (overall report preparation, mining, logistics, power and economic analysis); China Nerin Engineering (smelter design); DRA Global (mine surface infrastructure and metallurgical processing); Epoch Resources (tailings storage facility design); Golder Associates (hydrology models and recommendations); KGHM Cuprum R&D Centre (technical adviser on certain mining methods and geotechnical); Outotec Oyj (smelter technology); Paterson and Cooke (paste backfill plant design and surface/underground paste distribution system); SRK Consulting (mine geotechnical recommendations); Stantec Consulting International (mining and mineral reserves); Wood (mineral resources estimation); Kamoa Copper and SNEL, together with Stucky SA (engineering procurement and construction management – Turbine 5); Voith Hydro (contractor Turbine 5); China Nerin Engineering (basic engineering contract for the smelter); and Metso (smelter technology).