https://newsletter.en.creamermedia.com
  

SRK House, 265 Oxford Road, Illovo, 2196, South Africa

  

Platreef palladium/rhodium/nickel/platinum/copper/gold project, South Africa – update

Image of Platreef_Structural_Steel_Erection_Shaft_2_Ivanhoe

Photo by Ivanhoe Mines

9th August 2024

     

Font size: - +

Name of the Project
Platreef palladium/rhodium/nickel/platinum/copper/gold project.

Location
The Platreef project hosts an underground deposit of thick, platinum group metals (PGMs), nickel, copper and gold mineralisation on the northern limb of the Bushveld Igneous Complex, in Limpopo, South Africa. This is about 280 km north-east of Johannesburg and 8 km from the town of Mokopane.
On the northern limb, PGM mineralisation is primarily hosted within Platreef, a mineralised sequence traced for more than 30 km along strike. 

Project Owner/s
Ivanhoe Mines indirectly owns 64% of the Platreef project through its subsidiary, Ivanplats, and is directing all mine development work.

The South African beneficiaries of the approved broad-based, black economic-empowerment structure have a 26% stake in the Platreef project. The remaining 10% is owned by a Japanese consortium comprising Itochu Corporation; Japan Oil, Gas and Metals National Corporation; Itochu affiliate ITC Platinum Development; and Japan Gas Corporation.

Project Description
The project, within the Platreef’s southern sector, comprises two contiguous properties: Turfspruit and Macalacaskop. Turfspruit, the northernmost property, is contiguous with, and along strike from, Anglo Platinum’s Mogalakwena group of mining operations and properties.
The 2022 feasibility study on the Platreef project confirmed its potential to be the industry’s biggest and lowest-cost primary PGMs producer.

The  feasibility study is based on the detailed design and engineering scenario first presented in the November 2020 preliminary economic assessment, alongside the 2020 feasibility study, confirming the viability of a new phased development pathway to fast-track Platreef into production by the third quarter of 2024.

The 2022 feasibility study considers Phase 1 and Phase 2 development, including only one-third of Platreef’s indicated resources above an $80/t net smelter return cutoff.

The project has an indicated mineral resources estimated at 18.9-million ounces of palladium, 18.7-million ounces of platinum, 3.1-million ounces of gold and 1.2-million ounces of rhodium (a combined 41.9-million ounces PGMs plus gold), as well as 2.4-billion pounds of nickel and 1.2-billion pounds of copper at a 2 g/t platinum, palladium and rhodium plus gold (3PE+Au) cutoff.

Platreef’s inferred mineral resources contain an additional 23.8-million ounces of palladium, 23.2-million ounces of platinum, 4.3-million ounces of gold and 1.6-million ounces of rhodium (a combined 52.8-million ounces PGMs plus gold), as well as 3.4-billion pounds of nickel and 1.78-billion pounds of copper, also at a 2 g/t 3PE+Au cutoff.

The 2022 feasibility study is based on steady-state production of 5.2-million tonnes a year, as well as an accelerated ramp-up to steady state through the earlier development of Shaft 2.

Phase 1 production at Platreef includes an initial 700 000 t/y underground mine and 770 000 t/y capacity concentrator, targeting high-grade mining areas close to the project’s recently completed Shaft 1.

Phase 1 average production is estimated at 113 000 oz/y of 3PE+Au, and five-million pounds of nickel and three-million pounds of copper.

While the 700 000 t/y initial mine is operating using Shaft 1, the sinking of the project’s second, larger, Shaft 2, which will drive the Phase 2 expansion to 5.2-million tonnes a year, will progress simultaneously.

Once Shaft 2 is complete, two 2.2-million-tonne-a-year concentrator modules will be commissioned, and the initial concentrator will be ramped up to its full capacity of 770 000 t/y, increasing the steady-state production to 5.2-million tonnes a year.

Platreef’s Phase 2 expansion will result in its ranking as the world’s fifth-biggest primary PGMs mine on a palladium equivalent basis, with forecast production of 591 000 oz/y of 3PE+Au, as well as 26-million pounds of nickel and 16-million pounds of copper a year.

The Platreef 2022 feasibility study reflects only the initial two phases of development for the mine. If the remainder of Platreef’s indicated resources were to be converted to reserves, it would provide an opportunity to massively expand production.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The 2022 independent feasibility estimates an after-tax net present value, at an 8% discount rate, of $1.7-billion and an internal rate of return of 18.5% at long-term consensus metal prices. Payback is estimated at 7.9 years.

Capital Expenditure
Initial capital costs for Phase 1 are estimated at $488-million.

Expansion capital for Phase 2 is estimated at $1.5-billion, which may be partially funded by cash flows from Phase 1 and a project financing package.

Planned Start/End Date
First concentrate production for Phase 1 is planned for the third quarter of 2024; the Phase 2 expansion, based on the commissioning of Shaft 2, in 2027; and the commissioning of two 2.2-million-tonne-a-year concentrators in 2028 and 2029. 

Latest Developments
Construction of the Phase 1 concentrator was completed on schedule after the June 2024 quarter ended. 

Cold commissioning has started, with water being fed through the concentrator. The concentrator will be placed on care and maintenance until the second half of 2025, as Shaft 1 prioritises the hoisting of waste from the development required to bring forward the start of Phase 2.

Work continues on the updated feasibility study to accelerate Platreef Phase 2, as well as the preliminary economic assessment of the new Phase 3 expansion. Both studies are expected to be completed in the fourth quarter of this year.

Phase 3 will take the total Platreef processing capacity up to about ten-million tonnes a year. The new Phase 3 expansion is expected to consist of two additional 3.3-million-tonne-a-year concentrator modules, to be located adjacent to the phase 1 and 2 concentrators. Phase 3 is expected to rank Platreef as one of the world’s biggest and lowest-cost PGM, nickel, copper and gold producers. The ten-million-tonne-a-year concentrator capacity of the Phase 3 expansion will be 12.5 times greater than that of Phase 1, and 2.5 times greater than the processing capacity of the optimiSed Phase 2 expansion.

The completion of Shaft 2 will increase the total hoisting capacity for ore and waste development across all three shafts to more than 12-million tonnes a year.

Construction of Platreef’s Shaft 2 headgear now is about 60% complete. Ivanhoe reports that construction activities are advancing well on the installation of 1 124 t of internal structural steel inside Shaft 2’s headgear.

Key Contracts, Suppliers and Consultants
OreWin – Australia (overall report preparation and economic analysis, mineral reserve estimation and mine plan); Mine Technical Services – US (mineral resource estimation); SRK Consulting – South Africa (mine geotechnical recommendations); DRA Global – South Africa (process and infrastructure); Golder Associates Africa – South Africa (water and tailings management); Murray & Roberts Cementation (ventilation shaft sink and shaft repurposing).

Contact Details for Project Information
Ivanhoe Mines, tel +27 11 088 4300 or email info@ivanhoemines.com.
 


 

Edited by Creamer Media Reporter

Comments

sq:0.158 0.483s - 162pq - 2rq
Subscribe Now