Campelo, Bustelo and Monte Toural wind farms, Spain

22nd July 2022 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Campelo, Bustelo and Monte Toural wind farms, Spain

Name of the Project
Campelo, Bustelo and Monte Toural wind farms.

Location
The municipalities of Coristanco, Santa Comba and Carballo, A Coruña, in north-western Spain.

Project Owner/s
Siemens Gamesa and Greenalia.

Project Description
The project entails the construction of three wind farms – Campelo, Bustelo and Monte Toural – with a combined capacity of 110 MW.

They will provide enough electricity to power about 90 000 households or about a quarter of the population of the province of A Coruña.

The wind farms will also help to avoid the emission of almost 300 000 t/y of carbon dioxide, the equivalent to the emissions of about 170 000 vehicles.

Potential Job Creation
Not stated.

Capital Expenditure
Not stated.

Planned Start/End Date
The wind farms are scheduled to be commissioned by the end of 2023.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Siemens Gamesa, tel +34 944 03 73 52.
Greenalia, tel +1 918 519 7784 or email info@greenalia.us.