Name of the Project
Manatee gasfield project.
Location
East Coast Marine Area (ECMA), in Trinidad and Tobago.
Project Owner/s
Shell is the operator of Manatee with a 100% working interest under the sub-Block 6D Production Sharing Contract.
The ECMA is home to Shell’s largest gas-producing fields in Trinidad and Tobago, including Dolphin, Starfish, Bounty and Endeavour.
Project Description
The project will involve the construction of a normally unattended installation platform in the ECMA acreage, with eight development wells through a 110 km, 32" pipeline to the Shell-operated onshore Beachfield gas processing facility.
Once on line, Manatee is expected to reach peak production of about 104 000 bbl/d of oil equivalent.
Potential Job Creation
Not stated.
Capital Expenditure
Not disclosed.
Planned Start/End Date
A final investment decision on the project was made in July 2024. Production is targeted for 2027.
Latest Developments
None stated.
Key Contracts, Suppliers and Consultants
Not disclosed.
Contact Details for Project Information
Shell, tel +44 20 7934 5550.