Eastern System upgrade project, US
Name of the Project
Eastern System upgrade (ESU) project.
Location
The project will be co-located along Millennium Pipeline Company’s existing 393 km of right-of-way in New York, in the US.
Client
Millennium Pipeline Company.
Project Description
The ESU will be able to transport about 223 000 dekatherms a day from Millennium’s Corning compressor station to an interconnect with Algonquin gas transmission in Ramapo, New York.
The proposed project includes the construction of a 76 cm and 91 cm pipeline loop – the Huguenot loop – in Orange County, New York.
Millennium proposes to locate a majority of the pipeline loop overlapping with and adjacent to the permanent easement associated with its existing mainline – the Millennium pipeline.
In addition, Millennium proposes to:
• build and operate a new 22 400 hp compressor station (Highland compressor station) in Sullivan County, New York;
• build and operate additional compression of 22 400 hp at the Hancock compressor station in Delaware County, New York;
• modify the Ramapo meter station in Rockland County, New York;
• modify the existing Wagoner interconnect in Orange County, New York; and
• add additional pipeline appurtenant facilities at the existing Huguenot and Westtown meter stations in Orange County, New York.
Further, 12 temporary and eight permanent access roads, four contractor/pipe yards, and three staging areas are proposed for use during the construction of the project.
Jobs to Be Created
Not stated.
Value
Not stated.
Duration
Construction of the project is expected to start in the second half 2017, depending on receipt of the necessary approvals, to meet a target in-service date in September 2018.
Latest Developments
The US Federal Energy Regulatory Commission (FERC ) has concluded that the construction and operation of the project, with appropriate mitigating measures, will not constitute major federal action significantly affecting the quality of the human environment.
FERC has determined that potential impacts will be reduced with the implementation of Millennium’s proposed minimisation and mitigation measures, as well as the 18 additional measures recommended in the environmental assessment.
The deadline for comments on the environmental assessment was May 1.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
Millennium Pipeline Company, email info@millenniumpipeline.com.
Comments
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation