From green field to superstructure – Kusile Auxiliary Cooling Tower project
This article has been supplied.
Kusile power station is one of the new build power stations in the Eskom portfolio and will have an installed capacity of 4800 MW Once completed, Kusile will be the fourth largest coal fired power station in the world. We were awarded the contract to supply the auxiliary cooling towers for the plant in 2011 and have been working on the project since.
Two, four-cell, concrete induced draught cooling towers have been built to reject all the heat from the various auxiliary processes that support the six power generating units. Each cooling tower cell is designed to reject 27.6 MW at a flow rate of 1106 L/s to provide sufficient cooling to the various end users on the power station. Each cooling tower cell is fitted with a 30-foot fibreglass fan that is electrically driven to establish the air flow through the cooling towers. These fans are driven with variable speed drives to provide considerable energy savings for the client.
Currently we are nearing final handover for the complete project with minor construction activities and commissioning remaining for the Eastern Plant. At completion of this project it will be rewarding to see how this green field project materialised to be a superstructure that overlooks the adjacent farmlands. IWC’s cooling towers can clearly be seen on either side of the plant. We look forward to seeing how the towers perform as soon as the commissioning activities take place on site.
Comments
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation