C$2bn NPV for Baptiste nickel project
The newly released prefeasibility study (PFS) for the Baptiste project has established the nickel asset as a key strategic asset in the development of Canada’s critical minerals supply chain, says FPX president and CEO Martin Turenne.
The PFS demonstrates the Baptiste project’s potential as a high-margin, long-life, large-scale, and low-carbon mine with unparalleled flexibility to produce either a high-grade concentrate (60% nickel) for direct feed into the stainless steel industry or further refining into battery-grade nickel sulphate, cobalt precipitate, and copper concentrate products for the battery material supply chain.
The project has an after-tax net present value (NPV) of C$2.01-billion and an internal rate of return (IRR) of 18.6%.
“Despite the inflationary pressures observed in the mining industry in recent years, the study has yielded after-tax NPV and IRR superior to those observed in the 2020 preliminary economic assessment, reflecting greater engineering maturity and incorporating the several optimisations identified by our class-leading project team in regards to resource modelling, mine planning, process recovery and site design,” says Turenne.
The base case outlines an openpit mining project in central British Columbia which will produce an average of 59 100 t/y of nickel-in-concentrate over a 29-year mine life. The project will be developed in a phased approach, with an initial mill throughput rate of 108 000 t/d (Phase 1), followed by an expansion to 162 000 t/d (Phase 2) funded from free cash flow after the initial after-tax payback period of 3.7 years.
The refinery option outlines an off-site refinery to upgrade a portion of nickel-in-concentrate to produce 40 000 t/y of battery-grade nickel sulphate for the electric vehicle battery supply chain, with the balance of concentrate continuing to be directly supplied to the stainless steel industry. Along with battery-grade nickel sulphate, this option also supports the valorisation of cobalt and copper as refinery byproducts.
The total initial capital cost for the project is estimated to be $2.18-billion, with expansion capital cost of C$763-million.
The refinery option presents incremental capital expenditure of C$448-million with an incremental operating cost of $1.02 per pound of nickel (C1 cost of $0.79/lb nickel, including credits for cobalt and copper byproducts), resulting in a total NPV of $2.13-billion.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation