Compressor motors undergo rapid overhaul
KEEPING TO STANDARDS To ensure compliance with international standards, M&C Zambia sent a senior technician from Johannesburg to assist the local team
Electromechanical equipment manufacturer and ACTOM division Marthinusen & Coutts Zambia (M&C Zambia) noted, in a press release last month, that a smelter based in the Copperbelt had requested that it provide an in-country repair solution on the smelter’s two critical 4.5 MW compressor motors, with three weeks to complete the overhaul and commission the motors.
The scope of the work included the dismantling, cleaning and assessment of all parts, dynamically balancing the rotors at operating speed using M&C Zambia’s own 12-t balancing machine, supplying new bearing assembly parts, assembling the motors and no-load testing and laser aligning the motors on site.
“Upon dismantling both motors we identified that the stator coils indicated partial discharge and the stator wedges had deteriorated significantly over time,” explained M&C Zambia GM Eugene Lottering.
He noted that M&C Zambia consequently requested the M&C workshop in Cleveland, Johannesburg, to supply partial discharge treatment of the stator coils and to manufacture the replacement stator wedges.
To ensure that all the work complied with international standards, M&C also sent a senior technician from Johannesburg to assist with the local team on the contract.
Lottering noted that the M&C Zambia team is sufficiently experienced to approach and action various stages throughout the motor overhaul process.
“We successfully completed various medium voltage overhauls up to 4 650 kW. The motors were no-load tested at 11 kV with exceptionally good results and the customer then gave us the go-ahead to commission the motors,” Lottering elaborated.
He added that the installation of the motors on-site turned out to be a complicated procedure, especially when aligning the motors to the compressors.
The motors were tested on load, recording satisfactory vibration levels of below 1.34 mm a second, and were successfully installed and commissioned three days before the scheduled deadline for completion.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation