https://newsletter.en.creamermedia.com

Concor powers progress on fourways main roof works projects

Construction involves the installation of 550 concrete columns, ranging from 2.1 metre to 4.8 metre in height

Lightweight construction methods are used due to load restrictions on the rooftop, with spider cranes and dumpers used for erection activities

The project involves constructing a roof over the existing rooftop parking on Level 7 to provide covered parking for visitors while enabling the future installation of a solar photovoltaic (PV) system

Structural steel installation in progress on Parking Level 7 at Fourways Mall

Installation of the structural steel elements continues on the rooftop parking on Level 7 at Fourways Mall

Structural steel elements being installed atop the concrete columns, forming the framework for the new rooftop structure at Fourways Mall

Rehabilitation of the 8 000 m² access ring road was included in the scope of the project

As part of the scope, a steel structure is being constructed to support an 10 200 m² PV installation on the Northeastern rooftop parking area

24th February 2025

     

Font size: - +

This article has been supplied.

Concor has made substantial headway on the Fourways Main Roof Works Project, a pivotal component of the ongoing Fourways Mall Repositioning Project. As the largest shopping centre in Africa, with a Gross Lettable Area (GLA) of 178 000 m², Fourways Mall is undergoing significant upgrades to improve functionality and ensure future sustainability.

Martin Muller, Contract Manager at Concor, emphasises the importance of this initiative. “This project is significant not only for its sheer size—covering 50 000 m² of roof—but also for the complex logistical and technical challenges it presents. Despite these challenges, we are on track for completion by June 2025, a testament to Concor’s expertise in managing fast track projects in live retail environments.”

The project involves constructing a roof over the existing rooftop parking on Level 7 to provide covered parking for visitors while enabling the future installation of a solar photovoltaic (PV) system. As part of the scope, a steel structure is being constructed to support an 10 200 m² PV installation on the Northeastern rooftop parking area, further enhancing the mall’s sustainability.

Additionally, Concor is rehabilitating the access ring road, ensuring it meets the demands of the future.

Construction of the roof involves the installation of 550 concrete columns, ranging from 2.1 metre to 4.8 metre in height, to support a structural steel roof with sheeting. Rainwater drainage systems are being installed as part of the roof design.

Muller explains that the methodology requires the existing concrete surfaces to be prepped before drilling and dowelling the new columns into the mall’s current column structure. This ensures the load from the roof is transferred safely through existing columns and beams down to the foundations.

“Lightweight construction methods are being employed due to load restrictions on the rooftop, with spider cranes and dumpers used for erection activities,” he says. “Materials, including readymix concrete and structural steel, are delivered at street level and transported via trailers and dumpers to minimise disruption to mall operations.

On the Northeastern rooftop of Fourways Mall, a steel structure to support the installation of a solar PV system is being constructed on pre-existing concrete columns. This addition will not only provide renewable energy capability but also align with the broader goals of sustainability and energy efficiency.

Rehabilitation of the 8 000 m² access ring road is also well underway. “The completed ramp from Witkoppen Road to Fourways Boulevard has already been opened to the public, and this is a good indication of how our construction programme is geared to facilitate access for visitors to the mall.”

The process involves removing old kerbs and road components, addressing construction and bridge joints, upgrading drainage, applying waterproofing and laying a final asphalt layer. Traffic control measures including speed humps and road markings, are also being installed to ensure a safe and user-friendly experience for visitors.

Working within a live shopping environment poses unique challenges, but Concor is leveraging its extensive experience to minimise disruptions. Detailed construction management plans have been implemented including comprehensive signage to guide traffic and ensure the safety of visitors. In partnership with the Fourways Mall team, Concor is actively keeping stakeholders informed about project developments.

“This project showcases our ability to execute large-scale, technically demanding construction within active environments,” Muller says. “It’s all about balancing efficiency and safety while delivering high quality results.”

Scheduled for completion by June 2025, the Fourways Main Roof Works Project exemplifies Concor’s commitment to delivering complex infrastructure solutions that elevate both functionality and sustainability for South Africa’s retail sector.

Edited by Creamer Media Reporter

Comments

Showroom

The Southern African Institute of Mining and Metallurgy
The Southern African Institute of Mining and Metallurgy

The SAIMM started as a learned society in 1894 after the invention of the cyanide process that saved the South African gold mining industry of the...

VISIT SHOWROOM 
Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 21 February 2025
Magazine round up | 21 February 2025
21st February 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.113 0.201s - 168pq - 2rq
Subscribe Now