DRDGold nears completion of project to achieve better recoveries at FWGR
NYSE- and JSE-listed DRDGold says a project to convert the Driefontein 2 Plant (DP2) at the Far West Gold Recoveries (FWGR) surface retreatment operation, in Gauteng, to closed-circuit milling, is nearing completion.
The R80-million project will achieve a finer grind and, thereby, improve gold recovery rates, as well as enhance leaching conditions, reduce maintenance costs and increase water storage capacity in the current thickeners.
FWGR MD Kevin Kruger explains in a statement that, prior to its acquisition, DP2 treated 180 000 t a month of waste rock.
Post-acquisition, the plant was converted from closed-circuit hard rock milling to three-stage cyclone milling, in an open-circuit configuration, for the coarser fractions in the slimes reclaimed from the Driefontein 5 dump.
“The open-circuit configuration was used due to the limited thickening capacity of the original circuit, the need for a leach density of about 1.45, and to contain capital expenditure.
“Post commissioning and optimisation of the mill, improved gold recoveries of between 46% and 49% were achieved but fell short of recoveries of more than 50% which had been indicated from laboratory test work,” says Kruger.
As the new, regional plant planned as part of the previously announced second phase of development of FWGR will employ closed-circuit milling, it was decided to close the circuit on the current mill to align the two.
“This will ensure that higher-grade, coarser particles don’t get just a single pass through the mill but multiple passes until fine,” notes Kruger.
The conversion to closed-circuit milling entails replacing the two tertiary cyclones with a cluster of cyclones that will classify the mill discharge, together with the primary and secondary cyclone overflows.
The coarse cluster underflow will report back to the mill and the finer cyclone overflow to a new 45-m-diameter high-rate thickener.
The new thickener is required to adjust the slurry density to 1.45 for treatment in the carbon-in-leach plant.
The company expects to commission the converted plant in November.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation