El-Dabaa nuclear power plant, Egypt – update
 
																																																								
																
																																																	
Photo by Egyptian Nuclear Power Plant Authority
Name of the Project
El-Dabaa nuclear power plant (NPP).
Location
El-Dabaa, in Egypt, on the Mediterranean coast.
Project Owner/s
The Ministry of Electricity and Energy, represented by the Egyptian Nuclear Power Plant Authority (NPPA).
Project Description
El-Dabaa  will be the first nuclear power plant in Egypt. The project will involve the construction of an NPP comprising four Russian-designed VVER-1200 pressurised water reactors.
With a nameplate capacity of 4.8 GWe, the plant is expected to account for up to 50% of Egypt’s power-generation capacity to meet the country’s increasing demand for electricity.
Potential Job Creation
More than 20 000 people are working at the construction site.
Capital Expenditure
Not stated.
Planned Start /End Date
Unit 1 started construction in July 2022 and Unit 2 in November 2022. Applications to build units 3 and 4 were submitted in January 2022. Unit 3 was awarded a construction licence in March 2023.
Egypt expects the plant to reach full capacity in 2030.
Latest Developments
Installation of the reactor pressure vessel (RPV) for Unit 1 of the NPP is scheduled to start in mid-November.
The RPV, a central component that houses the reactor core and sustains the controlled nuclear chain reaction, was delivered to the site on October 21. Designed to withstand extreme pressure and temperature while ensuring leak-tightness, it is essential to the unit’s safety and reliability.
Manufactured at Rosatom’s Izhora plant, the vessel weighs more than 330 t.
The RPV was shipped from St Petersburg on October 1, arriving at El-Dabaa 20 days later through a purpose-built docking facility for oversized equipment.
Key Contracts, Suppliers and Consultants
Rosatom (pressurised water reactors); Atomenergomash and General Electric (turbine hall equipment); KHNP (construction of turbine islands); and Doosan Enerbility subcontractor – turbine islands).
Contact Details for Project Information
NNPA, tel +202 22616264 or email contact_us@nppa.gov.eg.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Comments
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
            Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
            Receive daily email newsletters
            Access to full search results
            Access archive of magazine back copies
            Access to Projects in Progress
            Access to ONE Research Report of your choice in PDF format
        
Option 2 (equivalent of R375 a month):
            All benefits from Option 1
            PLUS
            Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors 
            including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
        
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation


 
     
                    
                