https://newsletter.en.creamermedia.com
Coal|Energy|Eskom|Gas|Power|Repairs|Service|Slurry|System|Environmental
Coal|Energy|Eskom|Gas|Power|Repairs|Service|Slurry|System|Environmental
coal|energy|eskom|gas|power|repairs|service|slurry|system|environmental

Inoperative Kusile units could be returned earlier as Eskom reports good progress on temporary stacks

Eskom interim CEO Calib Cassim

Eskom interim CEO Calib Cassim

Photo by Creamer Media Chief Photographer Donna Slater

24th August 2023

By: Terence Creamer

Creamer Media Editor

     

Font size: - +

The temporary stacks being introduced at the Kusile coal power station, where three previously operational units have been out of service for ten months, have been built and interim CEO Calib Cassim has expressed optimism that the units could be returned to service earlier than previously indicated.

All three units, which have a combined capacity of 2 100 MW, became inoperable after the Unit 1 flue duct collapsed on October 23 due to a build-up of slurry. The collapse also compromised the unit 2 and 3 flue ducts, which share a common chimney with the Unit 1 flue.

In the face of intense loadshedding, Eskom secured environmental authorisation earlier this year to build three temporary flues that bypass Kusile’s flue gas desulphurisation plant until March 31, 2025. A decision that is being challenged in the courts.

The solution was proposed by Eskom in an effort to reintroduce the units earlier than would have been the case under a scenario where permanent repairs were implemented.

The temporary repair is expected to cost between R200-million and R250-million and will enable the three units to produce 720 MW apiece electricity while the permanent repairs are undertaken.

The cost of the permanent repair has not yet been finalised.

It was communicated previously that the first unit was likely to return towards the end of November, followed by the second unit in mid-December and the third on Christmas eve.

However, Cassim told editors on Thursday that the Kusile temporary stacks had been built and that it was, thus, possible that two of the units could begin producing by mid-November.

He indicated Unit 3 would be reintroduced first and was likely to be followed in quick succession by Unit 1, with the reintroduction of Unit 2 to take longer, owing to the configuration of the temporary solution.

In addition, Unit 5 could be synchronised to the grid in late November, which would add additional production from the power station, which currently only had Unit 4 operating. Although Unit 5 would operate only intermittently as tests were carried out ahead of full commercial operation.

Updates were also provided on the other major long-term outages and refurbishments that, together with Kusile, collectively involved 8 652 MW, including:

  • A repair to Medupi Unit 4, which Eskom expects to bring into operation in July 2024, using a second-hand stator;
  • The return of Koeberg Unit 1 on November 3, following a major outage slip during an extended outage to prepare the unit for a further 20 years of operation. Unit 1 is due to be returned ahead of a Unit 2 outage, which will start on November 7;
  • The replacement of Kriel cooling tower 4 by March 2024;
  • The completion of Majuba Unit 3’s re-bagging by March 2024; and
  • The cooling tower replacement at Tutuka by October 2024.

Chairperson Mpho Makwana said the initiatives formed part of the ‘Generation Operational Recovery Plan’ approved by the board earlier in the year following stakeholder consultations and which aimed to recover Eskom’s energy availability factor (EAF) to 70% by March 31, 2025.

“While there is a gradual improvement in some areas of generation, our recovery efforts have not fully yielded the desired outcomes, owing to the extensive work that needs to be done against a vulnerable and unreliable power system,” Makwana said, while describing the EAF goal as a stretch target.

Eskom failed to meet the 60% EAF target set for the end of March 2023, reporting an EAF of 56%.

Edited by Creamer Media Reporter

Comments

Latest News

An image showing the Self-Employed Material Recycler Training Programme
Plastics SA launches informal recycler training programme
Updated 1 hour 53 minutes ago By: Tasneem Bulbulia

Showroom

Weir
Weir

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
M and J Mining
M and J Mining

M and J Mining are leading suppliers of physical support systems as used by the underground mining industry. Our selection of products are not...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.096 0.202s - 184pq - 2rq
Subscribe Now