Eskom slaps conditions on emergency bidders to stop grid hogging
Eskom Holdings has imposed conditions to access the national grid on 1 850 MW worth of projects in South Africa that developers including Karpowership and Electricite de France SA have struggled to complete since they were awarded in March 2021.
The right to access the grid is “conditional based on the projects achieving certain milestones by December 2023,” Eskom said on Wednesday in a response to queries. “This is in line with Eskom’s objective to have projects connect to the grid as soon as possible and to discourage capacity hogging.”
Grid access is in short supply in South Africa. The amount of transmission capacity is insufficient, and in the wrong part of the country, for the swath of renewable energy projects being erected in a race to alleviate the country’s worst ever power outages. In December, a government award for 3,200 megawatts of wind energy failed because there was no grid connection available.
Delays have beset the so-called emergency power tender in which Karpowership won the rights to develop 1 220 MW of capacity. Acwa Power Co. and TotalEnergies SE are among the companies that also hold stakes in groups trying to develop projects under the program.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation