Florence copper project 40% complete, reports Taseko Mines

22nd October 2024

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

The Florence copper project is advancing on schedule and is now about 40% complete, keeping it on track for first production in about a year’s time.

In an update on Monday, CEO Stuart McDonald said that Taseko was pleased with progress in the first nine months of construction of the in-situ copper recovery (ISCR) project.

“With approximately 75% of total construction costs now committed, we expect total costs to be within 10% to 15% of the original $232-million estimate,” said McDonald.

Since construction commenced earlier this year, the bulk of activities have been focused on earthworks, concrete, and wellfield drilling. Installation of structural steel, tanks and process equipment is now under way.

McDonald stated that first copper production in late 2025 would be a transformative event for the company.

The Florence Copper ISCR facility will produce 85-million pounds a year of copper over the 22-year life-of-mine (LoM). Total LoM production is estimated at 1.5-million pounds of copper.

ISCR is an extraction method used for selected mineral deposit conditions as an alternative to openpit or underground mining methods.

Meanwhile, Taseko has applied to the US Department of Energy's Qualifying Advanced Energy Project Credit (48C) programme. 

McDonald said Florence Copper, which is set to become North America's lowest greenhouse-gas-intensity primary copper producer, qualifies as a critical materials project. 

“After submitting a concept paper in June, we received encouragement to proceed with the full application. We have now filed the application seeking a tax credit of up to $110-million, and we expect to hear whether Florence qualifies for the credit, or not, in January 2025,” he said.

Edited by Creamer Media Reporter

Comments

Showroom

Alco-Safe
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 
Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (11/04/2025)
11th April 2025 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.236 0.323s - 172pq - 2rq
Subscribe Now