Fortuna’s Séguéla construction on time despite heavy wet season
The construction of the Séguéla gold project, in Côte d’Ivoire, is continuing to track on time and on budget, despite a particularly heavy wet season, Fortuna Silver Mines COO for West Africa, David Whittle, reported on Thursday.
The project, which entails a 3 750 t/d mill at Séguéla, is about 83% complete and the first gold pour remains on target for mid-2023.
Fortuna said that deliveries continued to arrive in Abidjan, Côte d´Ivoire with all semiautogenous grinding (SAG) mill components now shipped. The last SAG mill package would arrive in early December.
Construction of the 90 kV transmission line and substation is nearing completion and on track to be energised in December.
The company further reported that about 565 000 m3 of water has collected in the water storage dam, which is in line with expectations and needs for commissioning and startup activities. Earthworks and high-density polyethylene lining of the tailings storage facility is on track for completion before the end of 2022.
The mining contractor has mobilised to site and has started establishment activities.
“The operation is now moving forward with its recruitment and on-boarding of key senior personnel allowing for the development of the operational procedures and systems in order to facilitate a smooth transition from construction into operation,” reported Whittle.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation