Koeberg Unit 1 on track to return to service in early November

The Koeberg nuclear power station

The Koeberg nuclear power station

17th August 2023

By: News24Wire

  

Font size: - +

Eskom says that the main mechanical work on replacing the steam generators at Koeberg's Unit 1 has been completed and it will return to service on 3 November. 

Koeberg's Unit 2 will be taken offline on 7 November, slightly later than anticipated two weeks ago, avoiding the problem that both units would be offline simultaneously.

In a statement on Thursday, Eskom said: 

Unit 1 of the Koeberg Nuclear Power Station reached a significant milestone on Friday, 28 July 2023, when the mechanical work of the replacement of the steam generators was completed. This is the most significant part of the scope which involved complex activities and it means that Eskom is now proceeding with the outage activities that could not be performed in parallel with the replacement of the steam generators. Immediately after the completion of the outage activities, the reactor will be reloaded with fuel, enabling the return to service of the Unit.

The new steam generators will first be tested and synchronised to the grid. 

Each unit of Koeberg generates 900MW when the plant is operating optimally, equal to two load-shedding stages. There have been numerous delays to the project to replace the steam generators on Unit 1, fuelling concerns that both units would be offline simultaneously. Eskom says it has now mitigated that risk. 

Eskom hopes that replacing the steam generators will result in a 20-year extension of Koeberg's operating licence. The new steam generators are also more efficient than the old ones and will produce an additional 27MW.

EXPLAINER | Koeberg nuclear plant: Why Eskom's crown jewel is so important

The replacement of the steam generators was first proposed in 2014. It has been held up by litigation and other issues.

Last year, an attempt to start the project in January had to be aborted after French contractors Framatome arrived to find that Eskom had not completed the containment building to store the radio-active old steam generators after removal. 

After the project restarted in January 2023, the timeline for the return of Unit 1 has shifted several times. 

Framatome has lodged hundreds of claims against Eskom for delays, while Eskom has issued counterclaims. As these will take a long time to resolve, Eskom does not have an accurate picture of the final costs of the projects. The lion's share of the contract was paid upfront to Framatome long before it actually commenced.  

While the risk of both units being offline simultaneously looks less likely to materialise now, Eskom announced recently that after the return of Unit 2 to generation, it will need to take Unit 1 out again for a 200-day outage. This is to test and repair, if necessary, the containment buildings of the reactor, following exposure to weather and seawater. The same is likely to be required for Unit 2. 

This means SA will continue to operate with only one unit at a time, well into 2025. 

Edited by News24Wire

Comments

Showroom

M and J Mining
M and J Mining

M and J Mining are leading suppliers of physical support systems as used by the underground mining industry. Our selection of products are not...

VISIT SHOWROOM 
VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.081 0.178s - 209pq - 2rq
Subscribe Now