Uranium developer Lotus Resources says production ramp-up at the Kayelekera uranium mine in Malawi is progressing, with the operation on track to reach nameplate output in the second quarter of 2026.
The company reported on Tuesday that the processing plant operated at about 80% utilisation during the second half of February, with milling rates reaching roughly 65% of steady-state levels.
Lotus said existing acid inventories and an ongoing delivery schedule would support the ramp-up to full production during the quarter.
Meanwhile, cold commissioning of the mine’s on-site acid plant has begun, with hot commissioning scheduled for April.
The company is also continuing work with converters to complete final product acceptance ahead of uranium deliveries.
MD Greg Bittar said in a statement that operational performance had improved steadily in recent weeks.
The company noted that once final product acceptance is achieved with one converter, it will be able to swap product between converters, providing greater flexibility across supply contracts and future uranium sales.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation