Monkey Island LNG, US

Image of LNG tanks

7th November 2025

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Monkey Island LNG.

Location
Monkey Island, Cameron Parish, Louisiana, US.

Project Owner/s
Monkey Island LNG.

Project Description
The facility will use cryogenic technology to liquefy about 3.4-billion cubic feet a day of natural gas to produce about 25-million tonnes a year of liquefied natural gas (LNG) to serve US offtakers and global export markets.

It will have up to five liquefaction trains, each with a capacity of five-million tonnes a year, and three 180 000 m3 
storage tanks on the Monkey Island site.

Potential Job Creation
Not disclosed.

Capital Expenditure
The project represents a $25-billion investment across two phases, positioning it among the biggest private energy infrastructure developments in North America.

Planned Start/End Date
Engineering and permitting are expected to start in 2026, with first LNG production targeted for the early 2030s.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
McDermott (engineering, execution planning and pricing for the facility’s engineering, procurement and construction phase. This is expected to transition into a final engineering procurement and construction contract aligned with the timing of Monkey Island LNG’s financing activities.).

Contact Details for Project Information
Monkey Island LNG, tel + 1 713 828 2800 or email info@mkyisland.com.
 

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Comments

Showroom

Monitor Distributors
Monitor Distributors

We at Hawk High Pressure Pumps specialise in industrial pumps and pumping systems. Our high pressure washing equipment is locally manufactured and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 28 November 2025
Magazine round up | 28 November 2025
28th November 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.175 0.392s - 191pq - 2rq
Subscribe Now