https://newsletter.en.creamermedia.com
Construction|Contractor|Electrical|Engineering|Mining|PROJECT|Raisebore|Safety|Surface|System|Training|Trucks|Underground|Equipment|Shaft Sinking|Raiseboring
Construction|Contractor|Electrical|Engineering|Mining|PROJECT|Raisebore|Safety|Surface|System|Training|Trucks|Underground|Equipment|Shaft Sinking|Raiseboring
construction|contractor|electrical|engineering|mining|project|raisebore|safety|surface|system|training|trucks|underground|equipment|shaft-sinking|raiseboring

Murray & Roberts Cementation gets creative with reeve block system at Platreef

Hoisting of a raisebore machine at Platreef

Ivanplats' Platreef mine, in Limpopo

Raisebore head and base

10th April 2025

By: Marleny Arnoldi

Deputy Editor Online

     

Font size: - +

Specialist shaft sinking and mining contractor Murray & Roberts Cementation has successfully completed a reeve block system project at Ivanplats’ Platreef project, in Limpopo.

Ivanplats needed an innovative solution to remove the reaming head in the shaft and avoid costly standing time at the end of a raiseboring exercise for Shaft 2.

“An acceleration of the build plan at Shaft 2 had seen construction under way on the shaft’s headgear last year before the completion of raiseboring,” explains Murray & Roberts Cementation senior project manager Fred Durand.

He points out that, when a reaming head reaches the surface at the end of a raiseboring process, the company normally uses a mobile crane from surface to help it dismantle the machine and load it onto trucks for removal from site.

“With the acceleration of the mine’s plan for Shaft 2 readiness, however, the construction of the headgear had been brought forward – so it was no longer feasible to position a crane in that area to remove the raisebore machine.

“The kibble winder was not installed yet, so we had to engineer our way out of this situation to reduce raisebore standing time costs,” Durand states.  

The solution started with a visit from one of Murray & Roberts Cementation’s rigging specialists from the company’s Bentley Park training and technical facility near Carletonville. His concept was to make use of a reeve block – or pulley block – system and winch which could be secured with limited steelwork at the bank elevation.

“We prepared a proposal which described how reeve blocks could be secured to the sinking sheave wheel floor steelwork by means of slings and beam clamps. We would then use an 8 t electrical winch, secured to the bank, to operate the reeve block system,” Durand says.

After the Murray & Roberts Cementation team was satisfied that the methodology would work, they conducted a rigorous risk assessment and prepared the necessary mitigation measures.

The plan was then ready for the client’s consideration – leading to a green light to proceed.

Personnel and equipment were soon mobilised and the necessary medicals and inductions completed in preparation for the reamer coming to surface at the end of its 950 m journey from underground.

“Our solution worked perfectly, allowing us to strip the raisebore machine and hoist it to the bank area – to be placed onto the support bridge and moved out of the shaft headgear. A mobile crane then lifted the machine onto the laydown area, ready for removal,” Durand notes.

He concludes that Murray & Roberts Cementation’s uncompromising approach to safe working practices ensured that this engineering solution was applied safely and efficiently within the tight timeframe.

The company’s core safety values recently earned it the landmark achievement of eight-million fatality-free shifts.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Latest News

An exhibit in the Sterkfontein Caves centre
Sterkfontein caves reopen to the public
Updated 19 minutes ago By: Schalk Burger

Showroom

Weir
Weir

Weir is a global leader in mining technology. We recognise that our planet’s future depends on the transition to renewable energy, and that...

VISIT SHOWROOM 
Weir
Weir

Weir is a global leader in mining technology. We recognise that our planet’s future depends on the transition to renewable energy, and that...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (11/04/2025)
11th April 2025 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.17 0.261s - 172pq - 2rq
Subscribe Now