Rio Tinto, Hancock to spend $1.6bn on new Pilbara iron-ore project
Rio Tinto and Hancock Prospecting will invest $1.61-billion to develop the Hope Downs 2 iron-ore project in the Pilbara, aiming to sustain long-term output from their joint operations in the region.
The project will target the Hope Downs 2 and Bedded Hilltop deposits and includes the development of two above-water-table pits with a combined capacity of 31-million tonnes a year.
Rio Tinto, which holds a 50% interest, will contribute $800-million. The joint venture has secured all required state and Federal approvals, the companies said on Tuesday.
“Approval of Hope Downs 2 is a key milestone for Rio Tinto, as we invest in the next generation of iron-ore mines in the Pilbara,” Rio Tinto Iron Ore CE Simon Trott said in a statement.
“These projects are part of our strategy to continue investing in Australian iron-ore and to sustain Pilbara production for decades to come.”
Construction is expected to create more than 950 jobs, and the project will support about 1 000 full-time equivalent roles once operational. First ore is scheduled for 2027, with mined material to be processed at the existing Hope Downs 1 facility.
Infrastructure works include new precincts, haul roads, rail crossings, and the realignment of a 6-km section of the Great Northern Highway.
Rio Tinto said it had worked with the Nyiyaparli, Banjima and Ngarlawangga Peoples and relevant authorities to manage heritage and environmental concerns during project planning.
Hope Downs 2 forms part of Rio Tinto’s replacement project pipeline, which the miner says will underpin a system capacity of 345-million to 360-million tonnes a year. The company plans to invest over $13-billion in its Pilbara iron-ore business between 2025 and 2027.
A prefeasibility study is also under way at the undeveloped Rhodes Ridge deposit.
The Hope Downs venture was established in 2006, with Rio Tinto and Hancock Prospecting having a shared history in the Pilbara dating back to the early 1960s. The first mine, Hope Downs 1, began production in 2007, followed by Hope Downs 4 in 2013.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation