Robex on track to deliver first gold at Kiniero

11th July 2025

By: Sabrina Jardim

Creamer Media Online Writer

     

Font size: - +

ASX-listed Robex Resources says it is on track to deliver first gold at its Kiniero gold project, in Guinea, in the fourth quarter of this year, after having received initial results from the Mansounia grade control drilling programme.

The company explains that the programme is designed to infill resource estimation drilling, enhancing geological confidence ahead of the planned first gold pour in the fourth quarter.

It notes that drilling has targeted areas within the proposed openpit design, focusing on zones identified for early-stage mining.

The majority of assays received to date are from the south-west portion of the Mansounia orebody, demonstrating strong mineral continuity.

Drilling at Mansounia is ongoing with 61 700 m complete. Robex says further assays will be reported as they are received.

The drilling was designed to cover the initial three months of mining the Mansounia pit design area to depths of 30 m to 50 m.

The assay results received to date are from the first 50% of the holes designed. Robex says the remainder of these holes will be completed and reported over the coming months.

Meanwhile, on July 9, the company secured an amendment to its $130-million facility agreement with Sprott Resource Lending, releasing $25-million from the cash sweep account to fund construction of the Kiniero project.

Robex says this is a positive development for its Guinean operations.

“We are pleased to report strong gold grades from this round of grade control drilling which adds further confidence to the mining proposition at Mansounia.

“The mineralised zones and grades defined by our grade control programmes are confirming our expectations of the Mansounia deposit,” says MD and CEO Matt Wilcox.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 
Carlisle TyrFil
Carlisle TyrFil

Flatproofing tire technology engineered to perform in extreme mining environments.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine cover image
Magazine round up | 11 July 2025
11th July 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.125 0.215s - 188pq - 2rq
Subscribe Now