St Ives hybrid microgrid project, Australia – update

Image of wind turbines and solar panels

25th July 2025

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
St Ives hybrid microgrid project.

Location
About 80 km south of Kalgoorlie, in Australia.

Project Owner/s
Gold and copper producer Gold Fields.

Project Description
The microgrid, the biggest in Gold Fields’ portfolio, will comprise 42 MW of wind power and 35 MW of solar power, and will provide 73% of the St Ives mine’s energy requirements.

The project will reduce the mine’s Scope 1 and 2 emissions by an estimated 50% in 2030 against the mine’s 2016 baseline.

Potential Job Creation
Not stated.

Capital Expenditure
A$296-million.

Planned Start/End Date
The full system is expected to be operational in 2026.

Latest Developments
The project is progressing on time and within budget. 

Gold Fields reported on July 16 that the foundations for seven wind turbines had been poured.

Every turbine foundation contains 800 m3 of concrete, supplied and poured by local contractor Westforce. Wind turbine components are expected to arrive at the site by September 2025.

Construction of the associated solar farm is also advancing, with more than half of the panel frames completed and the first of 66 000 solar panels delivered. Installation is set to start this month. The solar component is being developed in partnership with Pacific Energy.

Key Contracts, Suppliers and Consultants
Westforce (concrete); and Pacific Energy (solar plant).

Contact Details for Project Information
Gold Fields, tel +27 11 562 9700 or email info@goldfields.com.

Edited by Creamer Media Reporter

Comments

Showroom

Tractor & Grader Supplies

Tractor & Grader Supplies (TGS™): Your Trusted, Genuine Source for New Replacement Parts for Earthmoving, Construction and Mining Machinery

VISIT SHOWROOM 
Carlisle TyrFil
Carlisle TyrFil

Flatproofing tire technology engineered to perform in extreme mining environments.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 25 July 2025
Magazine round up | 25 July 2025
25th July 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.293 0.45s - 190pq - 2rq
Subscribe Now