Stalled South African power projects for 1 850 MW risk losing grid access
Companies yet to complete financing arrangements to build 1 850 MW of power-generation capacity in South Africa in terms of a government tender in 2021 may lose the right to connect to the national grid at the end of this month.
The access for projects by Karpowership, Acwa Power Co. and others relating to contracts for 2 000 MW awarded more than two years ago expires on July 31, national power utility Eskom said in an emailed response to questions. Scatec ASA has achieved so-called financial close for its 150 MW of projects.
The emergency-power programme has been beset by delays. Karpowership, the provider of gas-fired plants mounted on ships that won about 60% of the tender, has seen its plans thwarted by lawsuits and environmental challenges. A surge in construction costs globally has also complicated attempts by the bid winners to make financial arrangements.
Grid access is in short supply in South Africa. The amount of transmission capacity is insufficient, and in the wrong part of the country, for the swath of renewable energy projects being erected in a race to alleviate the country’s worst-ever blackouts. In December, a government award for 3 200 MW of wind energy failed because there was no grid connection available.
The amount of electricity that could be affected this month is equivalent to peak demand for Cape Town in winter.
Eskom is in talks with the Independent Power Producer Office (IPPO), which ran the tender, to decide on whether to extend the access, the company said.
The Department of Minerals Resources and Energy didn’t respond to requests for comment. The Development Bank of Southern Africa (DBSA) referred questions to the IPPO, which referred queries back to the department. The department and the DBSA oversee the independent producer authority.
If they lose entry to the grid, the companies will need to reapply, potentially incurring further delays to a process that was supposed to see electricity provided by August last year. It’s not clear whether new rules related to access, which will increase the amount of money developers must spend before they know whether they can access the network, will apply.
The IPPO has extended the deadline for financial close for the projects to December 31 from the end of June, two people familiar with the decision said, declining to be identified as the decision isn’t public.
In addition to Karpowership and Acwa, companies that hold stakes in winning bid consortiums include TotalEnergies SE and Electricite de France SA.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation