Vamma run-of-river hydropower plant modernisation, Norway
Name of the Project
Vamma run-of-river hydropower plant modernisation.
Location
Oslo, Norway.
Project Owner/s
Hafslund.
Project Description
Vamma is equipped with 12 turbine-generator units, including ten Francis and two large Kaplan turbines.
It has a total installed capacity of 343 MW and supplies an average of 1 580 GWh/y of electricity.
The project involves the upgrade of Unit 11’s turbine-generator units, increasing the capacity of the unit by 22%, from 100 MW to 122 MW.
It includes the dismantling, reassembling, testing and commissioning, as well as model testing and supply, of new components.
Potential Job Creation
Not stated.
Capital Expenditure
Not stated.
Planned Start/End Date
Commissioning of the fully upgraded Vamma 11 unit is expected in early 2028.
Latest Developments
None stated.
Key Contracts, Suppliers and Consultants
Andritz (Unit 11 upgrade).
Contact Details for Project Information
Hafslund, tel +47 24 11 65 00 or email post@hafslundeco.no.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation