JSE-listed platinum miner Wesizwe Platinum has identified various deficiencies at its Bakubung platinum mine’s processing plant, in Rustenburg, in North West, after a test run of the entire system.

Some of the snags include electrical malfunctioning of the flotation machine, a leak in the process water tank and the need for additional pipe support.

The technical team is currently addressing the deficiencies identified during the rest run, which, once resolved, will see the cold and hot commissioning of the processing plant in March or April.

The commissioning of the processing plant was originally earmarked to start in the fourth quarter of last year, however, it was delayed by the finalisation of an appeal process in relation to the Ministerial environmental authorisation granted for the construction of the mine’s tailings storage facility.

Early in 2022, Wesizwe expected production at Bakubing to start in the second half of 2023; however, it now appears that production may start earlier, depending on the repair and commissioning process.

The board is confident that the company can swiftly resolve any issues that may arise during the commissioning of the processing plant and start production as soon as possible.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Research Reports

Latest Multimedia

Showroom

SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 
Amsted Reelin image
Amsted Reelin

REELIN is Currently the largest supplier of Bearings to Transnet. We have contracts to supply bearings, draft gears slackadjusters and other...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

The above image depicts the helicopter airlifting the HVAC units onto  roof of Bedford Centre
Centre installs new HVAC system
19th September 2025 By: Lynne Davies

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.069 0.164s - 188pq - 2rq
Subscribe Now