https://newsletter.en.creamermedia.com
Africa|Energy|Eskom|Power|Projects|Renewable Energy|Solar|Technology
Africa|Energy|Eskom|Power|Projects|Renewable Energy|Solar|Technology
africa|energy|eskom|power|projects|renewable-energy|solar|technology

Wind bids fall well short of BW7 allocation, while PV bids far exceed provision

Solar PV with powerlines in the background

Photo by Creamer Media

19th August 2024

By: Terence Creamer

Creamer Media Editor

     

Font size: - +

REIPPPP BID WINDOW 7 LIST OF BIDS RECEIVED ON 15 AUGUST 2024  (0.28 MB)

The Independent Power Producer Office (IPPO) has confirmed that 48 onshore wind and solar PV bids with a combined capacity of 10 218 MW have been submitted under Bid Window Seven (BW7) of the Renewable Energy Independent Power Producer Procurement Programme (REIPPPP).

The bids were submitted on August 15, a deadline that was postponed from an initial date of April 30, largely owing to grid-access-related delays.

South Africa is seeking to procure 5 000 MW during the public procurement round, comprising 3 200 MW of wind and 1 800 MW of solar PV.

The solar PV allocation is substantially oversubscribed, with a total of 40 projects submitted, representing a combined capacity of 8 526 MW.

However, only eight onshore wind projects with a combined capacity of 1 692 MW have been submitted, falling 1 508 MW short of the capacity allocated to the technology for the round.

Ahead of the deadline, the South African Wind Energy Association cautioned that the imbalances in the prevailing rules for allocating grid access between projects competing under the REIPPPP as opposed to projects proceeding on the back of private power purchase agreements posed a challenge to wind projects under BW7.

The association also warned that, unless an alternative grid-access solution was found, BW7 could fail in a similar way as was the case during BW6.

During that previous bid window, none of the 23 wind projects that bid for a 3 200 MW allocation was selected as a preferred bidder, as the necessary grid capacity had been absorbed by private projects that were subjected to different grid-access rules.

Ahead of the BW7 deadline, Eskom sought permission from the National Energy Regulator of South Africa (Nersa) to reserve grid capacity for the REIPPPP to avert a recurrence of the BW6 failure.

In its application it argued that “without any form of protection, public procurement programmes remain incapable of competing with the much more agile and well-funded private sector energy procurement programmes”.

Nersa rejected the application, however, noting that Eskom had not identified the specific customers against which it intended discriminating, and also did not present objectively justifiable and identifiable differences regarding such customers, which were requirements for any approval for grid reservation.

Of the wind bids received, three are located in the Eastern Cape, two in the Western Cape, two in the Northern Cape and one in KwaZulu-Natal, with no bids made in grid-rich Mpumalanga despite various private wind projects advancing in the province.

The Free Sate has the highest number of solar PV bids with 20, followed by Limpopo (13), the North West (3), Mpumalanga (2) and the Northern Cape (2).

The IPPO will now evaluate the projects submitted under BW7 and it is anticipated that this process should be completed within three months of the bid submission deadline.

Edited by Creamer Media Reporter

Comments

Showroom

Victaulic
Victaulic

Since 1919, Victaulic’s innovative solutions and design services continue to increase construction productivity and reduce risk, ensuring projects...

VISIT SHOWROOM 
John Ratcliffe
John Ratcliffe

At John Ratcliffe, we are aftermarket specialists for heavy-duty on and off-road vehicles. We engineer and retrofit advanced safety systems, engine...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.256 0.406s - 303pq - 4rq
Subscribe Now