https://newsletter.en.creamermedia.com
Building|Construction|Contractor|Design|Energy|Generator|Generators|Installation|Nuclear|Power|PROJECT|Pumps|System|Systems|Technology|Water|Equipment
Building|Construction|Contractor|Design|Energy|Generator|Generators|Installation|Nuclear|Power|PROJECT|Pumps|System|Systems|Technology|Water|Equipment
building|construction|contractor|design|energy|generator|generators|installation|nuclear|power|project|pumps|system|systems|technology|water|equipment

Akkuyu nuclear power plant project, Türkiye update

Image of the closure of the thermal control layer of the Akkuyu NPP

Photo by Akkuyu Nuclear

24th May 2024

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Akkuyu nuclear power plant (NPP) project.

Location
Mersin, Türkiye.

Project Owner/s
Akkuyu Nuclear, comprising Inter RAO UES JSC, Rosenergoatom JSC, Atomtechenergo JSC, Atomenergoremont JSC and Rusatom Energy International JSC.

Project Description
The Akkuyu NPP will be based on an NPP-2006 serial project. The 4 800 MWe plant will comprise four VVER1200 reactors and is expected to meet about 10% of Türkiye’s electricity needs.

The power unit includes a reactor plant and a turbine plant.

The primary circuit is radioactive and comprises a reactor, four reactor coolant loops, four reactor coolant pumps, heating parts of four steam generators and one steam pressuriser.

The secondary circuit is not radioactive. It comprises steam generators; fresh steam conduits; one turbine unit comprising a turbine plant and a turbine generator; condensate pumps; a system of low-pressure regenerative heaters; a turbine condensate system; deaerators; a feedwater system, including feedwater pumps; and a system of high-pressure regenerative heaters.

The turbine is equipped with a condensing unit and regenerative installation for heating the feedwater and separators, with unregulated steam extraction for the NPP’s auxiliary needs and heating chemically treated water additives in the circuit.

Capital Expenditure
The project is estimated at $20-billion.

Planned Start/End Date
The aim is for the first unit of the plant to start supplying Türkiye's energy system in 2025, and for all four units to be operational by the end of 2028.

Latest Developments
The closure of the thermal control layer of the Akkuyu NPP has allowed for the installation of the turbine-generator set to proceed.

Turbine building roof installation has been completed at Unit 2, which took about three months.

The turbine building roof comprises nine prefabricated truss blocks, each

weighing between 95 t and 175 t, and 61 m long. The roof was assembled concurrently with the closure of the thermal control layer on two specially built benches using a Liebherr LR 13000 heavy crawler crane for installation.

Rosatom reports that the installation of the roof trusses in the turbine building required careful preparation and a high level of organisation and construction planning, as every truss was installed with an accuracy of 10 mm. 

Key Contracts, Suppliers and Consultants
Rosatom (construction of VVER-1200 reactors under a build, own, operate model); Titan2 Ic İçtaş İnşaat Anonim Şirketİ (construction contractor); GE Steam Power and AEM Technology, a joint venture between AtomEnergoMash and General Electric, or GE (design and supply of the equipment and systems for the whole conventional island); JSC Tyazhmash (core melt trap); and Nukem Technologies and NIKIMT-Atomstroy JSC (supply of the equipment for compacting SRW).

Contact Details for Project Information
Akkuyu NPP JSC, tel +90 312 442 60 00, fax +90 312 442 60 16 or email info@akkuyu.com.

Edited by Creamer Media Reporter

Comments

 

Showroom

Weir
Weir

Weir is a global leader in mining technology. We recognise that our planet’s future depends on the transition to renewable energy, and that...

VISIT SHOWROOM 
Condra Cranes
Condra Cranes

ISO-certified Condra manufactures overhead cranes, portal cranes, cantilever cranes and crane components: hoists, drives, end-carriages, brakes and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 13 December 2024
Magazine round up | 13 December 2024
13th December 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.277 0.438s - 196pq - 2rq
Subscribe Now