https://newsletter.en.creamermedia.com
Africa|Construction|Energy|Eskom|Generator|Power|PROJECT|Projects|Renewable Energy|Renewable-Energy|System|Systems
Africa|Construction|Energy|Eskom|Generator|Power|PROJECT|Projects|Renewable Energy|Renewable-Energy|System|Systems
africa|construction|energy|eskom|generator|power|project|projects|renewable-energy|renewable-energy-company|system|systems

Benchmarking study highlights slow pace of South Africa’s grid-connection system

Benchmarking study highlights slow pace of South Africa’s grid-connection system

Photo by Creamer Media

12th June 2024

By: Terence Creamer

Creamer Media Editor

     

Font size: - +

A new benchmarking assessment of South Africa’s electricity grid access queueing mechanisms indicates that Eskom’s systems are slower and less transparent than those being implemented in developed and developing countries analysed as part of the study.

Published by the RES4Africa Foundation, the report includes case studies of the grid management frameworks being implemented in Brazil, Chile, Italy and by PJM Interconnection in the US.

These systems have been assessed against five key performance indicators, namely: grid connection timeframes, the cost of connection, regulatory requirements, queue management, and transparency.

South Africa’s framework is in flux and is being governed currently by Interim Grid Capacity Allocation Rules (IGCAR).

These were introduced following the failure of the sixth public renewables round when none of the wind projects vying for a 3 200 MW allocation were selected because the capacity on which the projects were based had been absorbed by independent power producers being pursued on the back of private power purchase agreements.

Eskom argued that the new rules would prevent so-called grid hogging as they were based on prioritising shovel-ready projects rather than processing applications on a ‘first come, first served’ basis.

Separately, Eskom has also applied to the National Energy Regulator of South Africa (Nersa) for permission to preserve/reserve grid capacity for the public Renewable Energy Independent Power Producer Procurement Programme (REIPPPP) rounds so as to prevent any repeat of the failure of bid window six (BW6).

As a consequence, the bid submission deadline for BW7 was recently postponed to August 15 from May 30, a deadline that had itself been extended from the initial submission date of April 30.

RES4Africa Foundation Southern Africa project officer Mohau Nei reports that the IGCAR and Eskom’s proposed Gated Generator Connection Process, which still requires Nersa approval, were also tested against the five performance indicators.

When benchmarked, the selected countries and South Africa all had strengths and weaknesses, but South Africa lagged on grid connection time, regulatory requirements, queue management, as well as communication and transparency.

The study recommends that South Africa ratifies its rules as soon as possible to provide investors with predictability.

It also recommends that best practices be integrated, including through creating online systems for grid applications and to provide real-time visibility of queuing progress.

Nei adds that the study’s outcomes also point to the desirability of migrating to a clustered assessment methodology rather than case-by-case approvals so as to enable an analysis of the whole cluster’s impact on the grid.

This, she says, will facilitate equal access between REIPPPP projects and private projects as well as enable Eskom to revoke capacity allocated to projects that are failing to advance to construction.

Edited by Creamer Media Reporter

Comments

Showroom

John Deere (Pty) Ltd
John Deere (Pty) Ltd

In 1958 John Deere Construction made its first introduction to the industry with their model 64 bulldozer.

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (08/11/2024)
8th November 2024 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.279 0.389s - 208pq - 2rq
Subscribe Now