https://newsletter.en.creamermedia.com
Africa|afrisam|Casting|composite|Concrete|Construction|Design|Efficiency|Energy|Engineering|Environment|Eskom|formwork|generation|Infrastructure|Innovation|Modular|Pipes|Power|PROJECT|Projects|Reinforcing|Resources|Roads|Safety|SECURITY|Services|Sustainable|System|Training|transport|Water|Maintenance|Power Generation|Power-generation|Environmental|Infrastructure|Operations
Africa|afrisam|Casting|composite|Concrete|Construction|Design|Efficiency|Energy|Engineering|Environment|Eskom|formwork|generation|Infrastructure|Innovation|Modular|Pipes|Power|PROJECT|Projects|Reinforcing|Resources|Roads|Safety|SECURITY|Services|Sustainable|System|Training|transport|Water|Maintenance|Power Generation|Power-generation|Environmental|Infrastructure|Operations
africa|Afrisam|casting|composite|concrete|construction|design|efficiency|energy|engineering|environment|eskom|formwork|generation|infrastructure|innovation|modular|pipes|power|project|projects|reinforcing|resources|roads|safety|security|services|sustainable|system|training|transport|water|maintenance|power-generation|power-generation-industry-term|environmental|infrastructure|operations

Concor's landmark Kendal ADF project wins Best Projects Awards

The Kendal Ash Disposal Facility project stands out for its vast scale, covering an area of approximately 2.5km by 3km

Some of the infrastructure involved had irregular shapes due to the boundaries in which construction work was conducted

Engineering work included diverting an existing stream with clean water channelled for 3km around the new ADF area

Built to withstand 1-in-100-year floods, the constructed stream is about 30m wide, with a base width of 10m and embankments of 10m on each side

Another aspect of the Kendal ADF project is the 16km of V-shaped water channels, comprising 8km of channels for clean water and 8km for polluted water which run side by side. Image shows these under construction

Two HDPE lined earth dams have been constructed close to the ADF, with Dam 1 for polluted water and Dam 2 for clean water. Each dam is compartmentalised into two basins. Image shows these under construction

The ADF design includes a subsoil drainage system, allowing clean groundwater to run into the clean water dam, which has an impermeable liner system placed over this infrastructure, and another drainage system installed above the liner

Construction of all access roads formed part of the scope of the project

The full scope of the project included the new 65 hectare ADF itself, two HDPE-lined earth dams or basins for clean water, two similar dams for polluted water, silt traps, an extensive 16km V-drain system with channels for clean and dirty water, access road construction and a major stream diversion

HDPE geomembrane of 1,5mm thickness was used on the base of the dams, as well as on the inner side slopes, on top of which a geotextile layer was placed for protection (image on left). Then a 50mm thick concrete blinding layer was constructed, before a 150mm thick ballast layer comprising a 30MPa concrete slab, was placed over the entire dam basin footprint (image on right

7th November 2024

     

Font size: - +

This article has been supplied as a media statement and is not written by Creamer Media. It may be available only for a limited time on this website.

Concor won two prestigious Construction World Best Projects 2024 Awards for its impressive work, undertaken in joint venture with Lubocon Construction, on the Ash Disposal Facility (ADF) expansion at Eskom’s Kendal Power Station near Ogies, Mpumalanga. Placed as the winner in the AfriSam Innovation Award for Sustainable Construction Category, the projects also secured a Highly Commended in the Civil Engineering Contractors Category. These awards highlight Concor's commitment to environmentally responsible engineering and infrastructure innovation, especially within the power generation sector.

The project is notable for its sheer size and complexity, covering approximately 2.5km by 3km. The construction scope included a new 65 hectare ash disposal site, two lined dams for clean and polluted water, a 16km V-drain water channel system, silt traps, access roads and a significant 3km stream diversion. This expanded ADF enables Kendal Power Station to manage ash disposal sustainably, extending its operational life by almost another decade. The project’s comprehensive design ensures compliance with stringent environmental regulations, a critical aspect of maintaining energy production while safeguarding surrounding ecosystems.

The 3km stream diversion, a prominent element of the project, channels clean water around the ADF to prevent contamination. Designed to withstand extreme conditions, the diversion is built for 1-in-100-year flood levels and is reinforced with erosion control structures including gabion linings and Reno mattresses. The gabions alone required more than 4,100 hand-filled baskets, using over 42,000 tons of rock and employing 120 workers for 19 months.

This diversion not only protects water resources but also aids in the restoration of a natural ecosystem as the gabions and river mattresses help stabilise the banks and encourage revegetation with wetland materials. A biodegradable blanket further prevents erosion on the banks, creating a supportive habitat for aquatic life and vegetation.

Environmental compliance was central to the ADF’s design, particularly the prevention of groundwater contamination. The facility was lined with a robust composite system, comprising two 150mm thick layers of low permeability clay sourced from on-site excavation. This clay layer, combined with an impermeable HDPE liner and a subsoil drainage system, forms a durable barrier that prevents seepage into the groundwater. Above this liner, a leachate collection system of HDPE pipes in a herringbone layout helps capture and manage potential contaminants, further safeguarding the environment.

The ADF project also included the construction of two strategically located dams—one for polluted water and the other for clean water. Dam 1, designated for polluted water, has a capacity of 130,000m³ while Dam 2, for clean water, can hold up to 257,000m³. These dams were compartmentalised for greater control and efficiency and included a 150mm concrete ballast layer for structural integrity. Concor applied a patented PVC formwork system during the dam construction allowing faster and more efficient casting of concrete panels, significantly reducing time and labour.

Facing a strict project timeline, Concor and Lubocon maintained continuous operations, leveraging around-the-clock shifts during dry months to make the most of favourable weather. This rigorous approach allowed the project to meet environmental licensing deadlines with construction commencing in June 2020 and completing in June 2024.

Despite challenging timelines and complex requirements, Concor successfully maintained its Zero Lost Time Injury (LTI) rate across a total of 2.2 million hours worked. The company’s “Zero Harm” strategy and Visible Felt Leadership principle, involving active oversight by experienced safety officers, were instrumental in fostering a strong safety culture on-site.

The Kendal ADF project also set a high standard for community engagement and corporate social investment (CSI). Concor and Lubocon worked closely with Eskom to implement social initiatives in the surrounding communities. This included the addition of modular classrooms and a kitchen at a local primary school.

Furthermore, the project achieved 85% local content, sourcing materials, transport, security services, and other supplies from nearby towns, thereby boosting local economies. Over its lifecycle, the project employed around 450 local workers, including subcontractors, and partnered with community structures to ensure equitable access to employment.

Skills development was also a priority, with training provided in fields such as civil engineering, safety, administration, and mobile plant operation. By the project’s end, over 850 locals had received valuable skills training, equipping them for future employment opportunities.

Concor’s approach to environmental management extended to on-site practices that minimised ecological impact. For instance, a subsoil drainage system captures clean groundwater and diverts it into the clean water dam, reducing reliance on municipal water sources and promoting water reuse. Additionally, the project’s stream diversion was lined with local wetland material to encourage natural vegetation growth. Regular maintenance will prevent alien plant invasion and protect the waterway from erosion.

This award-winning project is an exemplary model of sustainable construction, reinforcing Concor’s “Build to Last” philosophy, which emphasises longevity and value. The company’s commitment to quality was underscored by using innovative techniques, such as K Form shutters, which allowed the dam basins’ concrete work to be completed two months ahead of schedule. Every project component, from sluice gates to HDPE geomembranes, underwent stringent quality checks, ensuring a robust final product that would serve the community and environment effectively.

Concor’s achievements in the Kendal ADF project underscore the company's capability to deliver on large-scale complex infrastructure projects with a strong emphasis on environmental stewardship, community engagement, and technical excellence. This project not only supports Eskom’s operational goals but also contributes significantly to South Africa's broader energy security by ensuring a stable ash disposal solution aligned with environmental standards.

Edited by Creamer Media Reporter

Comments

Showroom

Victaulic
Victaulic

Since 1919, Victaulic’s innovative solutions and design services continue to increase construction productivity and reduce risk, ensuring projects...

VISIT SHOWROOM 
VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (01/11/2024)
1st November 2024 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.156 0.261s - 201pq - 2rq
Subscribe Now