Concor’s landmark Kendal ADF project wins Best Projects Awards
The Kendal Ash Disposal Facility project stands out for its vast scale, covering an area of about 2.5 km by 3 km.
Some of the infrastructure involved had irregular shapes due to the boundaries in which construction work was conducted.
Engineering work included diverting an existing stream with clean water channelled for 3 km around the new ADF area.
Built to withstand 1-in-100-year floods, the constructed stream is about 30 m wide, with a base width of 10 m and embankments of 10 m on each side.
Another aspect of the Kendal ADF project is the 16 km of V-shaped water channels, comprising 8 km of channels for clean water and 8 km for polluted water which run side by side. Image shows these under construction.
This article has been supplied.
Construction and mining services company Concor won two prestigious Construction World Best Projects 2024 Awards for its impressive work, undertaken in joint venture with Lubocon Civils, on the Ash Disposal Facility (ADF) expansion at Eskom’s Kendal Power Station near Ogies, Mpumalanga. Placed as the winner in the AfriSam Innovation Award for Sustainable Construction Category, the project also secured a Highly Commended Award in the Civil Engineering Contractors Category. These awards highlight Concor's commitment to environmentally responsible engineering and infrastructure innovation, especially within the power generation sector.
The project is notable for its sheer size and complexity, covering about 2.5 km by 3 km. The construction scope included a new 65 hectare ash disposal site, two lined dams for clean and polluted water, a 16 km V-drain water channel system, silt traps, access roads and a significant 3 km stream diversion. This expanded ADF enables Kendal Power Station to manage ash disposal sustainably, extending its operational life by almost another decade. The project’s comprehensive design ensures compliance with stringent environmental regulations, a critical aspect of maintaining energy production while safeguarding surrounding ecosystems.
The 3 km stream diversion, a prominent element of the project, channels clean water around the ADF to prevent contamination. Designed to withstand extreme conditions, the diversion is built for 1-in-100-year flood levels and is reinforced with erosion control structures including gabion linings and Reno mattresses. The gabions alone required more than 4 100 hand-filled baskets, using over 42 000 tons of rock and employing 120 workers for 19 months.
This diversion not only protects water resources but also aids in the restoration of a natural ecosystem as the gabions and river mattresses help stabilise the banks and encourage revegetation with wetland materials. A biodegradable blanket further prevents erosion on the banks, creating a supportive habitat for aquatic life and vegetation.
Environmental compliance was central to the ADF’s design, particularly the prevention of groundwater contamination. The facility was lined with a robust composite system, comprising two 150 mm thick layers of low permeability clay sourced from on-site excavation. This clay layer, combined with an impermeable HDPE liner and a subsoil drainage system, forms a durable barrier that prevents seepage into the groundwater. Above this liner, a leachate collection system of HDPE pipes in a herringbone layout helps capture and manage potential contaminants, further safeguarding the environment.
The ADF project also included the construction of two strategically located dams—one for polluted water and the other for clean water. Dam 1, designated for polluted water, has a capacity of 130 000 m³ while Dam 2, for clean water, can hold up to 257 000 m³. These dams were compartmentalised for greater control and efficiency and included a 150 mm concrete ballast layer for structural integrity. Concor applied a patented PVC formwork system during the dam construction allowing faster and more efficient casting of concrete panels, significantly reducing time and labour.
Facing a strict project timeline, Concor and Lubocon maintained continuous operations, leveraging around-the-clock shifts during dry months to make the most of favourable weather. This rigorous approach allowed the project to meet environmental licensing deadlines with construction starting in June 2020 and completing in June 2024.
Despite challenging timelines and complex requirements, Concor successfully maintained its Zero Lost Time Injury rate across a total of 2.2-million hours worked. The company’s “Zero Harm” strategy and Visible Felt Leadership principle, involving active oversight by experienced safety officers, were instrumental in fostering a strong safety culture on-site.
The Kendal ADF project also set a high standard for community engagement and corporate social investment. Concor and Lubocon worked closely with Eskom to implement social initiatives in the surrounding communities. This included the addition of modular classrooms and a kitchen at a local primary school.
Further, the project achieved 85% local content, sourcing materials, transport, security services and other supplies from nearby towns, thereby boosting local economies. Over its lifecycle, the project employed around 450 local workers, including subcontractors, and partnered with community structures to ensure equitable access to employment.
Skills development was also a priority, with training provided in fields such as civil engineering, safety, administration and mobile plant operation. By the project’s end, over 850 locals had received valuable skills training, equipping them for future employment opportunities.
Concor’s approach to environmental management extended to on-site practices that minimised ecological impact. For instance, a subsoil drainage system captures clean groundwater and diverts it into the clean water dam, reducing reliance on municipal water sources and promoting water reuse. Additionally, the project’s stream diversion was lined with local wetland material to encourage natural vegetation growth. Regular maintenance will prevent alien plant invasion and protect the waterway from erosion.
This award-winning project is an exemplary model of sustainable construction, reinforcing Concor’s “Build to Last” philosophy, which emphasises longevity and value. The company’s commitment to quality was underscored by using innovative techniques, such as K Form shutters, which allowed the dam basins’ concrete work to be completed two months ahead of schedule. Every project component, from sluice gates to HDPE geomembranes, underwent stringent quality checks, ensuring a robust final product that would serve the community and environment effectively.
Concor’s achievements in the Kendal ADF project underscore the company's capability to deliver on large-scale complex infrastructure projects with a strong emphasis on environmental stewardship, community engagement and technical excellence. This project not only supports Eskom’s operational goals but also contributes significantly to South Africa's broader energy security by ensuring a stable ash disposal solution aligned with environmental standards.
CAPTIONS
CONCOR PIC 01 : The Kendal Ash Disposal Facility project stands out for its vast scale, covering an area of about 2.5 km by 3 km.
CONCOR PIC 02 : Some of the infrastructure involved had irregular shapes due to the boundaries in which construction work was conducted.
CONCOR PIC 03 : Engineering work included diverting an existing stream with clean water channelled for 3 km around the new ADF area.
CONCOR PIC 04 : Built to withstand 1-in-100-year floods, the constructed stream is about 30 m wide, with a base width of 10 m and embankments of 10 m on each side.
CONCOR PIC 05 : Another aspect of the Kendal ADF project is the 16 km of V-shaped water channels, comprising 8 km of channels for clean water and 8 km for polluted water which run side by side. Image shows these under construction.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation