Congo says $14bn Inga dam on track despite disagreements
The Democratic Republic of Congo remains committed to building a $14-billion dam on the Congo River, even as the project is bogged down in disagreements between its developers, according to the government agency overseeing the project.
Congo envisages an 11 050 MW facility that can export 5 000 MW to South Africa, the Agency for the Development and Promotion of the Grand Inga Project, which falls under the presidency, said in a statement. Mining companies in Congo would get about 3 000 MW, and the national electricity company the remaining 3 000 MW.
The Inga III dam would be the biggest hydroelectric power station on Africa’s second-longest river. After Congo asked two groups of developers – one Chinese, one Spanish – to submit a joint proposal last year, talks between the partners have broken down over “serious differences” regarding the development and shareholding of the project, China Three Gorges Corp, the main company in the Chinese consortium, said in a September 20 letter.
A week-long series of meetings between the partners in March ended without a deal, and China Three Gorges said it didn’t see the need for further talks.
Patrick Kabuya, head of communications for the government agency known as ADPI, said the project would proceed. “Negotiations are continuing with all sides,” he said in an interview in Kinshasa, the capital.
A conference hosted by Congo’s presidency in August proposed scaling back the facility to a previous 4 800 MW version – a design the Chinese and Spanish groups believe isn’t economically viable.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation