Congo’s $14bn dam project threatened by disagreements

28th October 2019

By: Bloomberg

  

Font size: - +

Serious disagreements between groups of Spanish and Chinese developers that want to build a 11 000 MW hydropower plant in the Democratic Republic of Congo (DRC) may scuttle plans for the $14-billion project, according to a report.

The Inga III dam would be the biggest hydroelectric power station on Africa’s second-longest river and provide much-needed electricity to Congo and other nations, including South Africa. After the Congolese government in 2017 asked two competing groups – one Chinese, one Spanish – to merge, the partners submitted a joint proposal in November last year.

However, they were unable to agree on the project’s development and the percentage of each party’s share, the main company in the Chinese consortium, China Three Gorges Corp, said in a September 20 letter to Bruno Kapandji, the head of Congo’s Agency for the Development and Promotion of the Grand Inga Project, or ADPI. The letter was published Monday in a report from New York University’s Congo Research Group and Belgium-based advocacy organization Resource Matters.

Inga III is part of a long-delayed plan known as Grand Inga that’s eventually intended to harness as much as 40 000 MW of power from the Congo River. Management of the project was criticized under former President Joseph Kabila for its lack of transparency. In July 2016, the World Bank halted a $73-million grant for environmental and social studies after Kabila put the Inga agency under his direct control.

Two dams built on the same stretch of the Congo River more than three decades ago, Inga I and Inga II, still provide most of the nation’s power.

‘RE-OPEN DOSSIER’
The near-collapse of the current group of developers provides an opportunity for Kabila’s successor, Felix Tshisekedi, “to completely re-open the Inga III dossier, both in terms of its own capacity as well as that of its investors,” the Congo Research Group and Resource Matters said in the report.

“This ambitious project must be revisited to ensure that the Congolese population benefits from it,” they said.

Nobody answered the phone at the offices of China Three Gorges in Congo’s capital, Kinshasa, and Beijing. The company that heads the Spanish consortium, AEE Power SA, declined to comment. ADPI didn’t immediately respond to phone calls, text messages and emails.

Most of the electricity generated by Inga III is meant for South Africa, other African markets or Congo’s copper and cobalt miners. In 2013, South Africa committed to purchasing 2 500 MW generated by the facility and late last year indicated it might double that amount.

While Kabila appointed the Chinese and Spanish groups as co-developers a year ago, Tshisekedi, who assumed office in January, has yet to approve the consortium’s bid, and the partners are waiting to hear whether they will be granted exclusive rights to finance technical, environmental and social studies, as well as attract lenders.

The government, meanwhile, may consider scaling back Inga III to an earlier, 4 800 MW design the Spanish and Chinese partners don’t see as economically viable. At a conference hosted by Congo’s presidency in August, Maximilien Munga, head of the Energy Ministry’s project coordination and management unit, said the smaller version was “underpinned by proven demand” and could be completed faster.

VISITS HALTED
China Three Gorges said in the letter that it “remains ready to actively cooperate with the Congolese party to develop Inga III.” However, “important problems in China and the Ebola epidemic in your country” have prevented executives from visiting Congo, it said.

Congo has struggled to contain the second-worst Ebola outbreak, which has killed more than 2 100 people since it was first discovered in August 2018.

Edited by Bloomberg

Comments

 
 

Showroom

Victaulic
Victaulic

Since 1919, Victaulic’s innovative solutions and design services continue to increase construction productivity and reduce risk, ensuring projects...

VISIT SHOWROOM 
Avlock International
Avlock International

Avlock International is a leading manufacturer and distributor of Specialized Fastening Systems.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 13 December 2024
Magazine round up | 13 December 2024
13th December 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.174 0.266s - 194pq - 2rq
Subscribe Now