Nkomati mine tailings pipeline project set for completion next month

PROJECT PROGRESS
All the pipes required for the project have been delivered and more than 4 500 m of piping have been installed to date

PROJECT PROGRESS All the pipes required for the project have been delivered and more than 4 500 m of piping have been installed to date

19th January 2018

By: Mia Breytenbach

Creamer Media Deputy Editor: Features

     

Font size: - +

Multidisciplinary engineering services provider TDS Projects Construction, in partnership with Robor Pipe Systems, has started construction of a 13-km-long tailings pipeline for the Nkomati nickel mine’s Onverwacht site, in Mpumalanga.

The project is on track for successful completion next month, according to TDS Projects Construction.

Nkomati represents one of the largest nickel reserves in South Africa, having estimated reserves of 408.6-million tonnes of ore containing about 1.35-million tonnes of nickel metal.

The tailings pipeline will connect to the cross-valley tailings storage facility at the Onverwacht site.

TDS was contracted for the project by Robor Pipe Systems, with whom TDS has a long-standing working relationship as one of its preferred subcontractors.

According to TDS operations director Willie Pieters, the two firms frequently collaborate on pipeline projects.

“Owing to the competitive nature of the market, TDS Projects Construction and Robor decided to work together on projects where pipes were to be supplied and installed. Robor is one of the major pipe suppliers in South Africa and chose to partner with us based on our expertise, capability and excellent safety record,” he says.

The planned pipeline will consist of a 400 mm pipe column. The highest point will reach 1 468 m above sea level and the lowest point 1 200 m above sea level.

The pipe column design is suitable for pumping slurry at 64 bar. TDS Projects Construction started construction in October. All the pipes required for the project have been delivered and more than 4 560 m of piping has been installed.

While pipeline installations of this magnitude are not uncommon in the industry, Pieters believes that this particular project highlights some of Robor’s unique hallmarks.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

Environmental Assurance (Pty) Ltd.
Environmental Assurance (Pty) Ltd.

ENVASS is a customer and solutions-driven environmental consultancy with established divisions, serviced by highly qualified and experienced...

VISIT SHOWROOM 
WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (08/11/2024)
8th November 2024 By: Martin Creamer
Magazine round up | 08 November 2024
Magazine round up | 08 November 2024
8th November 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.06 0.154s - 170pq - 2rq
Subscribe Now