Developer of Ethiopian geothermal plant targeting financial close in 2019
A private company implementing a $2-billion geothermal power plant in Ethiopia is hoping to attain financial close next year to enable it to deliver the first 50 MW by 2021.
Tulu Moye Geothermal Operations (TMGO) says negotiations are at an advanced stage with potential financiers of the 520 MW Tulu Moye geothermal project, which involves the exploration, design, development, financing, construction, operation and maintenance of a power plant located in the Omoria region, about 100 km south-east of Addis Ababa, the country's capital.
TMGO CEO Darrell Boyd says the company is targeting a delivery date of 2021 for Phase 1 of the project, which involves an installed capacity of 50 MW. The first phase is projected to cost $250-million.
TMGO is owned by Meridiam, a leading global infrastructure fund manager, and Reykjavik Geothermal, a specialised developer that has been present in Ethiopia for a long time.
TMGO has submitted an application to the Multilateral Investment Guarantee Agency, a member of the World Bank, for a guarantee of up to 15 years for its investment in the project. The guarantee is for risks like breach of contract, expropriation and war and civil disturbance.
Meanwhile, TMGO has also secured a $1.1-million grant from the US Trade and Development Agency (USTDA) to coordinate a feasibility study supporting the development of Phase I of the project. The study will be conducted by US firm Delphos International.
“The USTDA is pleased to support this important project, which will foster energy diversification and improve access to affordable and reliable electricity in Ethiopia,” says USTDA director of Congressional and public affairs Thomas R Hardy.
He adds that the grant supports the goals of the US government's Power Africa initiative, which seeks to promote economic growth and investment in Africa through investments in the energy sector.
The Tulu Moye project is intended to provide Ethiopia with adequate, reliable and affordable energy to power its manufacturing sector and other industries.
In December last year, Ethiopian Electric Power signed implementation agreements and power purchase agreements for the Tulu Moye project and the Corbetti geothermal project.
The two projects involve the construction of power plants with a combined installed capacity of 1 000 MW at an estimated cost of $4-billion.
The entire Tulu Moye project will be built over eight years.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation