Gas Growth Integrated Project – Ratawi oilfield, Iraq

Image of oil rig

Photo by ©Bloomberg

14th November 2025

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Gas Growth Integrated Project (GGIP) – Ratawi oilfield.

Location
Southern Iraq.

Project Owner/s
The project is led by TotalEnergies (45%, operator) alongside its partners Basra Oil Company (30%) and QatarEnergy (25%).

Project Description
The GGIP is intended to advance the development of Iraq’s natural resources and strengthen its electricity supply. The 4-in-1 project includes recovering gas – currently flared at three oilfields, in southern Iraq, to fuel power plants, build a 1 GWac solar farm, establish a seawater treatment plant and redevelop the Ratawi oilfield. The Ratawi oilfield is one of Iraq’s lowest-emission oil sites.

Phase 1 aims to increase production to 120 000 bbl/d.

The launch of Phase 2 (full field development) will increase production to 210 000 bbl/d, with no routine flaring. The 160-million cubic feet a day of associated gas produced will be fully processed, owing to the 300-million-cubic-feet-a-day Gas Midstream Project (GMP). The GMP, which will also treat previously flared gas from two other fields, in southern Iraq, will deliver processed gas to the national grid, where it will fuel power plants with a production capacity of about 1.5 GW, providing electricity for 1.5-million Iraqi households.

Potential Job Creation
Currently, 2 700 workers have been mobilised at the GGIP site, including 2 000 Iraqis. The workforce is expected to increase to about 7 000 Iraqis at the peak of construction.

Capital Expenditure
The GGIP will require capital expenditure of $13-billion.

Planned Start/End Date
Phase 1 of the Ratawi oilfield is expected to come on stream by early 2026, and Phase 2 by 2028. The GMP started construction in early 2025. An early production facility to process 50-million cubic feet a day of associated gas will start in early 2026, together with the Ratawi Phase 1 oil production.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
Not disclosed.

Contact Details for Project Information
TotalEnergies, tel +33 1 47 44 46 99 or email presse@totalenergies.com.
 

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Comments

Showroom

WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 
Bell Equipment
Bell Equipment

As one of South Africa's leading manufacturers, Bell Equipment distributes and exports its wide range of heavy equipment globally to mining,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.116 0.204s - 186pq - 2rq
Subscribe Now