Golden Pass export terminal project, US

Golden Pass export terminal project, US

9th May 2025

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Golden Pass export terminal project.

Location
Sabine Pass, Texas, in the US.

Project Owner/s
Golden Pass LNG Terminal, a partnership between QatarEnergy and ExxonMobil affiliates.

Project Description
The project will add natural gas liquefaction and export capabilities to the existing terminal at Sabine Pass.

The current terminal facilities include five 155 000 m3 liquefied natural gas (LNG) storage tanks, two marine berths capable of offloading various-sized ocean-going LNG carriers, and process facilities capable of regasifying LNG to produce about two-billion standard cubic feet of natural gas a day.

The project will use the existing state-of-the-art tanks, berths and pipeline infrastructure while new facilities for natural gas pretreatment and liquefaction will be built.

The project includes construction of three liquefaction process trains, with a total output of about 18-million metric tons a year.

Each process will have an estimated nominal output of 5.2-million metric tons a year; associated treatment, power and utility systems; and interconnections to existing import facilities and controls. Modifications will also be made to the existing facilities, in addition to expanding the facility’s storm protection levee system, and increasing other safety and security features.

Potential Job Creation
The project will create thousands of jobs during the construction phase and more than 200 permanent jobs once operational.

Capital Expenditure
$10-billion.

Planned Start/End Date
The project is expected to be completed by November 2029.

Latest Developments

Key Contracts, Suppliers and Consultants
Not disclosed.

Contact Details for Project Information
Golden Pass LNG, tel +1 713 324 6800/+1 877 246 4728 or email Info@GoldenPassLNG.com.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

Weir
Weir

Weir is a global leader in mining technology. We recognise that our planet’s future depends on the transition to renewable energy, and that...

VISIT SHOWROOM 
The Southern African Institute of Mining and Metallurgy
The Southern African Institute of Mining and Metallurgy

The SAIMM started as a learned society in 1894 after the invention of the cyanide process that saved the South African gold mining industry of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 09 May 2025
Magazine round up | 09 May 2025
9th May 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.147 1.669s - 174pq - 2rq
Subscribe Now