Gulpur hydropower project, Pakistan
Name and Location
Gulpur hydropower project, Pakistan.
Client
Mira Power, a special purpose vehicle incorporated in Pakistan.
Project Description
The project involves the construction of a 102 MW run-of-river (RoR) hydroelectric power project. The project includes a dam, intake structure and a powerhouse.
Energy will be evacuated through an existing transmission line that runs about 200 m from the powerhouse. A 650 m road segment to connect the construction site to the main road will be built.
All the project structures will be located near Barali on the Poonch river about 11 km downstream of Kotli town and about 6 km downstream of the confluence of Bann Nullah river with the Poonch river.
The intake structure and intake portal of the power tunnel will be located on the west bank of the Poonch river, 150 m upstream of the weir structure on the eastern face of a ridge. The powerhouse and outlet will be located on the right bank of the Poonch river about 700 m downstream of the dam structure. The dam will be a concrete gravity dam 66 m high, 205 m long, with a six gate spillway (11.5 m × 6) with an overall width of 86.5 m.
Value
The total project cost is estimated at $365-million, including contingencies.
Duration
Not stated.
Latest Developments
The International Finance Corporation (IFC) proposed an A loan of $60 million, up to $45-million from IFC acting in its capacity as implementing entity for the Managed Co-Lending Portfolio Program and additional mobilisation of up to $25-million through an IFC B loan/parallel loan.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
Mira Power, tel +92 300 5003651.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation