Hinkley Point C nuclear power plant project, UK – update

Image of HinkleyC steam generator transport

Photo by EDF Energy

17th May 2024

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Hinkley Point C nuclear power plant (NPP) project.

Location
On a site to the west of the existing Hinkley Point A and B power stations in West Somerset, in the UK. 

Project Owner/s
Nuclear New Build, a subsidiary created by EDF Energy.

Project Description
The project will involve the construction, operation and maintenance of a new nuclear power station, known as Hinkley Point C.

The development will include:
• two UK European pressurised reactors with a combined output of 3 200 MW, associated buildings and a plant;
• staff facilities, offices, workshops and storage buildings;
• cooling water tunnels and associated infrastructure, including a fish recovery and return system;
• fuel and management facilities, including for spent fuel and intermediate waste;
• a sea wall, incorporating a public footpath;
• a national-grid 400 kV substation and overhead power lines on site;
• a public information centre;
• a temporary jetty;
• an emergency access road;
• access and parking facilities for workers, visitors and deliveries; and
• a temporary accommodation campus, including 510 bed spaces.

The new power plant will be capable of generating up to 3 260 MW.

The power station is expected to operate for about 60 years.

Potential Job Creation
Construction and operation of Hinkley Point C will create about 25 000 employment opportunities and up to 1 000 apprenticeships. An estimated 64% of the project’s construction value is predicted to go to UK companies.

Capital Expenditure
Delays arising from the Covid-19 pandemic will increase the cost of the project to £23-billion.

Planned Start/End Date
The start of electricity generation from Unit 1 is expected in June 2026, compared with the end of 2025 as initially announced in 2016.

Latest Developments
The first of eight 520 t steam generators has been delivered to the construction site.

The 25-m-long steam generators will take heat from the nuclear reactors to create steam to power the world’s largest turbines. The generator has arrived in time for the fit-out of the new power station, which will result in the first nuclear reactor installed later this year.

Four generators will be placed in each reactor building, operating at an average temperature of 295 °C for at least 60 years.

Key Contracts, Suppliers and Consultants
Kier BAM Joint Venture (site preparation works); Framatome SA (pressure vessel and steam generators); Bouygues and O’Rourke JV (construction contract); Sarens NV (assembling the world’s biggest crane at the site to aid construction at a later stage); MHI (pump sets); Trilium (subcontractor to MHI); Tecnatom (preoperational inspection services); BGEN (electrical and instrumentation solutions); and GE Steam Power Systems (conventional power islands).

Contact Details for Project Information
EDF Energy, tel +44 1138 207117.

To watch Creamer Media's latest video reports, click here
 

Edited by Creamer Media Reporter

Comments

Projects

Showroom

GreaseMax
GreaseMax

GreaseMax is a chemically operated automatic lubricator.

VISIT SHOWROOM 
M and J Mining
M and J Mining

M and J Mining are leading suppliers of physical support systems as used by the underground mining industry. Our selection of products are not...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 22 November 2024
Magazine round up | 22 November 2024
22nd November 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.139 0.296s - 198pq - 2rq
Subscribe Now