Hydro project achieves commercial operation
The Nyamwamba 11, 7.8MW hydropower project reached its PPA Commercial Operation Date (COD) on March 17, 2022. The Uganda Electricity transmission Company limited (UETCL) was awarded the completed powerplant a COD letter after successfully completing testing and commissioning for the Nyamwamba II, 7.8 MW hydropower project.
The Nyamwamba II project is part of the efforts from the Ugandan government to use renewable energy to strengthen and diversify the country’s electricity infrastructure. The new capacity will support the local government to reach its 100% renewable energy target for the Kasese district in the country.
The project’s total investment cost is about $22-million and is 100% owned by renewable energy project developer and investor Serengeti Energy.
The project is the second hydro project on the Nyamwamba river and the third hydro project of Serengeti Energy to become operational in the country. It will provide clean and reliable energy to the local power supply.
Construction of the project commenced in October 2019 and was faced with several challenges brought about by the Covid-19 pandemic. The project development and construction teams and their advisors were up to the task and surmounted the challenges to complete the project.
The Regional Liquidity Support Facility, an initiative by German State-owned development bank KfW and African Trade Insurance Agency, to mitigate short term liquidity risks on independent power projects in Africa is supporting the project, and documentation will be executed shortly.
Project financier EAIF obtained its final credit approval in February 2022 and financial close is targeted in Q2, 2022.
"Access to reliable and affordable electricity is a key prerequisite for economic development. “The Nyamwamba II project demonstrates our strong commitment to renewable energy development in Uganda,” Serengeti Energy CEO Chris Bale.
“We would like to appreciate the Ugandan government, specifically the Ministry of Energy and Mineral Development of Uganda and UETCL, for their continued support in the development and construction of the project. A special appreciation as well to our shareholders KfW, Norfund and NDF that have been pivotal in making this project possible.”
Comments
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation