Polihali tunnel completion marks LHWP milestone

6th September 2024

By: Natasha Odendaal

Creamer Media Senior Deputy Editor

     

Font size: - +

After seven months of tunnelling on the Polihali transfer tunnel construction site, the Lesotho Highlands Development Authority (LHDA) has achieved the successful breakthrough of the upper intake tunnel into the lower intake tunnel.

The successful completion of the intake tunnels brings the LHDA one step closer to realising the full potential of the Polihali dam: boosting water transfers to South Africa, increasing the volume of hydropower generated in Lesotho, enhancing the livelihoods of Basotho and contributing to the economies of Lesotho and South Africa.

The intake tunnels will allow water from the 5 042 ha Polihali reservoir to enter the transfer tunnel for delivery to the Katse reservoir, the centre point of the Lesotho Highlands Water Project.

The authority will now embark on the next two critical phases of the project, including the safe start of the impoundment of the Polihali reservoir, made possible by the collapse of the upper tunnel into the lower one.

The process allows for a controlled and secure increase in water levels up to the lower tunnel, which can then be temporarily sealed.

The second phase enables continuous debris removal from the remaining tunnel works.

As construction progresses towards its connection with the access adit, debris can be efficiently cleared through the upper intake tunnel without interrupting the impoundment process, the LHDA said in a statement to Engineering News & Mining Weekly.

“This efficient operation is crucial for maintaining project momentum while ensuring the structural integrity of the tunnels.”

Key milestones in the Polihali transfer tunnel works include the excavation of the 450 m long tunnel, which started on January 16 and was completed on August 19; the completion of the 370-m-long lower intake tunnel on August 5 and the ongoing excavation of the connecting tunnel.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Research Reports

Showroom

Universal Storage Systems (SA)
Universal Storage Systems (SA)

South African leader in Steel -Racking, -Shelving, and -Mezzanine flooring. Universal has innovated an approach which encompasses conceptualising,...

VISIT SHOWROOM 
Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.164 0.254s - 172pq - 2rq
Subscribe Now