Minato waste-to-energy refurbishment project, Japan
Name of the Project
Minato waste-to-energy (WtE) refurbishment project.
Location
Tokyo, Japan.
Project Owner/s
Clean Authority of Tokyo.
Project Description
The WtE facility comprises three stoker-type incinerators and related equipment, each with a capacity of 300 t/d, and can generate up to 22 MW of electricity.
The project involves the refurbishment and improvement of the incinerators and related equipment, including the refuse feeder and incinerator furnace, the equipment for ash treatment, a bag filter, a scrubber, boilers, power generators and steam condensers, as well as electric instrumentation and water supply systems.
Using nickel-base alloy cladding technology to offset boiler tube thinning, upgrading the main equipment for steam turbines and power generators, and improving combustion with control technologies using infrared sensors will allow for long-term stable incineration and operation.
The facility will also use high-efficiency motors and inverters for electric components to increase energy efficiency. These measures will reduce carbon dioxide emissions by about 4% a year, helping to curb global warming.
Potential Job Creation
Not stated.
Capital Expenditure
The contract is valued at $73-million.
Planned Start/End Date
The project is expected to be completed in January 2023.
Latest Developments
None stated.
Key Contracts, Suppliers and Consultants
Mitsubishi Heavy Industries Environmental & Chemical Engineering Co, a subsidiary of Mitsubishi Heavy Industries, or MHI (facility renovation of Minato WtE plant).
Contact Details for Project Information
MHI, email mediacontact_global@mhi.co.jp.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation