N2 Wild Coast Toll Road megabridge project – Mtentu bridge, South Africa – update

Artist's impression of the Mtentu brdige

Photo by Sanral

23rd August 2024

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
N2 Wild Coast Toll Road (N2WCTR) megabridge project – Mtentu bridge. 

Location
The bridge will be built over the  Mtentu river gorge, near Lusikisiki, in South Africa’s Eastern Cape province.

Project Owner/s
South African National Roads Agency Limited (Sanral).

Project Description
The  Mtentu bridge forms part of the N2WCTR project.

The 1.13-km-long bridge, which includes a 260-m-long main span, will be one of the longest main-span-balanced cantilever bridges in the world. Only ten prestressed concrete girder bridges worldwide have a main span of 260 m or longer. Reaching heights of more than 220 m above the river valley, it will displace the Bloukrans bridge, in the Western Cape, as the highest bridge in Africa and the southern hemisphere. The 141-m-tall Pier No 9 (equivalent to a 40-storey building in height) will also be the tallest bridge pier in Africa and the southern hemisphere.

Consequently, the construction of the Mtentu bridge is technically a highly challenging project, with its remote location and local social dynamics adding its complexity.

Potential Job Creation
The project has a local labour contract participation goal of 4%. This will result in at least R141-million being paid to local labour, creating a minimum of 1 550 full-time-equivalent jobs for local skilled and unskilled persons during the contract.

About 2 350 full-time-equivalent jobs will be created during construction, and while job numbers will vary during the contract, an average of 520 jobs will be created every month over 50 months, of which 350 will be filled by locals.

Capital Expenditure
R4.05-billion.

Planned Start/End Date
Construction started in August 2023.

Provided there are no significant delays, construction is expected to take 50 months, with the project expected to be completed at the end of 2027.

Latest Developments
Sanral has reported that R250-million has been spent on the contract to date and 248 local labourers have been employed. 

Construction of the access roads to the piers and the third trial blasting operation, as well as geotechnical investigative drilling for Pier 2 and Pier 11, are ongoing. 

Key Contracts, Suppliers and Consultants
Dissing+Weitling (bridge design); Mota-Engil Construction South Africa and China Communications Construction Company (main contractors); HVA JV (Msikaba and Mtentu bridge consultants comprising CH2M and SMEC); 

Adjacent Contracts
WBHO/H&I JV (main contractor), Knight Piésold (lead consultant – Msikaba to Mtentu); and KBK Engineers (lead consultant – Mtentu to Kulumbe).

Contact Details for Project Information
Sanral, email pressoffice@nra.co.za.

Edited by Creamer Media Reporter

Comments

Projects

Image of wind farm with sun in the background
Lålax Wind Farm, Finland
Updated 6 hours ago By: Sheila Barradas

Showroom

John Thompson
John Thompson

John Thompson, the leader in energy and environmental solutions through value engineering and innovation, provides the following: design, engineer,...

VISIT SHOWROOM 
Alcohol Breathalysers
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.154 0.313s - 196pq - 2rq
Subscribe Now