NAL on track and under budget - Sayona
PERTH (miningweekly.com) – Lithium developer Sayona Mining on Friday said that the restart of the North American Lithium (NAL) operation, in Quebec, is tracking to plan, while the project budget has dropped by nearly C$2-million.
Sayona told shareholders that the restart of NAL was on track for the first quarter of 2023, with procurement 94% complete, and 95% of the required permits received.
Meanwhile, the overall project budget has also been lowered to C$95.5-million from the previous C$97.75-million owing to reductions in the scope of work, with commitments to date of C$41.6-million compared to the planned C$45.4-million.
Sayona and its joint venture partner Piedmont formally approved the restart of the NAL operations at a budget of C$98-million. The NAL restart project has been funded through cash contributions by both Sayona and Piedmont, each company having successfully completed significant capital raises in the first half of 2022.
Sayona noted that the project team’s continuous communication and close contact with vendors had resulted in innovative strategies to maintain the planned schedule, with contingency plans in place to mitigate any potential delays to equipment deliveries.
“We are delighted to see the continued progress towards the recommencement of lithium production at NAL in the first quarter of 2023. Our project team has overcome potential challenges due to proactive forward planning and the early ordering of critical long‐lead equipment items, while the near completion of permitting and procurement puts us in an excellent position,” Sayona MD Brett Lynch said.
“Our recent achievements have been recognised by investors, as seen by our promotion to the S&P/ASX200 index, and I would like to thank shareholders for their continued support. With the right team in place, an ESG‐friendly operation due to Québec’s clean and green hydro power and the backing of key stakeholders, we are well placed for further growth as the leading lithium producer in North America.”
An earlier prefeasibility study estimated that the 1.5-million-tonne-a-year NAL operation could deliver 4.4-million tonnes of spodumene concentrate over a mine life of 27 years.
Comments
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation