https://newsletter.en.creamermedia.com

NTCSA says independent transmission projects must not reflect as balance-sheet liability

NTCSA interim CEO Segomoco Scheppers

NTCSA interim CEO Segomoco Scheppers

Photo by Creamer Media Chief Photographer Donna Slater

6th December 2024

By: Terence Creamer

Creamer Media Editor

     

Font size: - +

The head of the National Transmission Company South Africa (NTCSA) has confirmed that the entity’s board will insist that any independent transmission projects (ITPs) procured in the coming years should not reflect as a liability on the new entity’s balance sheet.

However, interim CEO Segomoco Scheppers tells Engineering News & Mining Weekly that he remains confident that such a framework will be found in the coming months, and that an ITP pilot procurement programme will be launched next year, as has been signalled by government.

The Ministry of Electricity and Energy and the National Treasury view the procurement of ITPs as key to accelerating the implementation of the NTCSA’s ambitious Transmission Development Plan (TDP).

The TDP involves the building of 14 500 km of new transmission lines and the addition of 210 transformers by 2034, which are required to integrate 56 GW of new generation. It represents a fivefold increase in delivery over the next ten years compared with the previous decade and it has been estimated that it could involve investments worth some R390-billion.

In the Medium-Term Budget Policy Statement, the National Treasury confirmed that a pilot ITP procurement process was being prepared for the second half of 2025 using a build-operate-and-transfer (BOT) model and supported by a new credit-guarantee vehicle.

The World Bank’s Multilateral Investment Guarantee Agency has been playing a central role in designing the instrument, which will seek to mimic the role that government guarantees conventionally play to de-risk projects for ITP developers but without exposing the national balance sheet to yet more contingent liabilities.

It has also been confirmed that the Independent Power Producer Office, which has overseen the public procurement of more than 7 GW of operational renewable-energy capacity since 2011, will oversee the pilot programme to procure South Africa’s first ITPs.

Work is also under way to finalise the regulations for the publication of the Ministerial determinations needed to facilitate the procurement process, as well as the selection of mature ITP prospects from within the NTCSA’s existing TDP pipeline.

However, Scheppers says the credit- guarantee vehicle is not designed to shield the NTCSA’s balance sheet.

Additional work is, thus, still needed to finalise a design that is acceptable to the entity, whose board is said to be reluctant to “encumber” an already-stretched balance sheet further.

The board has, thus, endorsed only a so-called build-and-transfer solution, which is described as engineering, procurement, and construction (EPC) with finance, while management continues to explore the BOT-type solutions that are more typical globally.

“One of the pegs that has been placed in the ground by the board is that the ITPs should be properly off-balance-sheet,” Scheepers tells Engineering News & Mining Weekly.

“This is something that government has accepted and National Treasury has said they will look at solutions.”

Meanwhile, the NTCSA is pressing ahead with its own-build initiatives using a combination of traditional contracting models, including EPC contracting, which was introduced recently.

“NTCSA has identified 47 priority projects that can be fast-tracked to accelerate TDP delivery.

“These projects are expected to unlock 37 GW of new generation capacity by 2034.”

Besides conventional investments into powerlines and transformers, NTCSA is also preparing to start adding synchronous condensers to provide inertia, voltage support and short-circuit power as the penetration of inverter-based renewables rises.

Seven synchronous-condenser sites have been selected, including Gromis, Aggeneis, Ferrum, Gamma, Koruson, Grassridge and Vuyani.

The entity’s new corporate plan, which is under development, is expected to cater for the addition of the first synchronous condensers, with research under way to assess whether generators from decommissioned coal units could be repurposed to play the role.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

 

Showroom

Weir
Weir

Weir is a global leader in mining technology. We recognise that our planet’s future depends on the transition to renewable energy, and that...

VISIT SHOWROOM 
Alco-Safe
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 13 December 2024
Magazine round up | 13 December 2024
13th December 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.246 0.334s - 170pq - 2rq
Subscribe Now