Olkiluoto 3 European pressurised reactor project, Finland – update


Olkiluoto 3 European pressurised reactor
Photo by Teollisuuden Voima Oyj
Name of the Project
Olkiluoto (OL) 3 European pressurised reactor (EPR) project.
Location
Western Finland.
Project Owner/s
Electricity producer Teollisuuden Voima Oyj (TVO).
Project Description
The OL3 nuclear power plant unit includes an EPR adjacent to the existing OL1 and OL2 units.
OL3 has an output of about 1 600 MW and produces about 13 TWh/y of electricity to meet about 14% of Finland's electricity demand.
Potential Job Creation
Not stated.
Capital Expenditure
$11-billion, about three times what was initially estimated.
Planned Start/End Date
Construction of OL3 started in 2005 and entered operation in 2023, significantly behind schedule.
Latest Developments
TVO has completed its final acceptance – the final takeover – of Olkiluoto 3, based on the fulfilment of the terms and conditions in the plant supply contract.
Key Contracts, Suppliers and Consultants
Areva–Siemens Consortium, comprising Areva GmbH, Areva NP SAS and Siemens AG (plant supplier).
Contact Details for Project Information
TVO, tel +358 2 83 811.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation