ASX-listed Black Cat Syndicate has started refurbishment works on the processing facility at the Paulsens gold mine, in Western Australia.

The company, which in November unveiled a new restart plan for the gold mine, is advancing procurement of long lead items, it said in a statement on Friday.

“Our team has been systematically working through the processing plant conducting maintenance work, as well as setting detailed plans for future refurbishment works. Work to date has been extremely productive with significant upside identified, particularly in the crushing circuit.

“Long lead items have been or are in the process of being ordered. We are also starting to engage with mining contractors and equipment suppliers. Activities will progressively step up as our additional financing becomes available,” said Black Cat MD Gareth Solly.

The November 2023 restart study, which is based on 406 000 oz resource, delivers 163 000 oz of gold at an all-in sustaining cost of A$1 836/oz, over a 4.2-year mine life.

At a gold price of A$2 900/oz, Paulsens will deliver operating cashflow of A$110.6-million. Each A$100/oz change in the gold price impacts the operating cashflow by A$16-million.

Edited by Creamer Media Reporter

Comments

 

Showroom

John Ratcliffe
John Ratcliffe

At John Ratcliffe, we are aftermarket specialists for heavy-duty on and off-road vehicles. We engineer and retrofit advanced safety systems, engine...

VISIT SHOWROOM 
Rittal
Rittal

Rittal is a world leading provider of top-quality integrated systems for enclosures, power distribution, climate control, IT infrastructure and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 13 December 2024
Magazine round up | 13 December 2024
13th December 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.231 0.326s - 192pq - 2rq
Subscribe Now