https://newsletter.en.creamermedia.com
Copper|Dewatering|Engineering|Pumps|Underground|Water|Operations
Copper|Dewatering|Engineering|Pumps|Underground|Water|Operations
copper|dewatering|engineering|pumps|underground|water|operations

Ivanhoe confirms on schedule start of Stage 2 dewatering at Kakula

The Kakula mine

The Kakula mine

18th September 2025

By: Creamer Media Reporter

     

Font size: - +

TSX- and OTCQX-listed Ivanhoe Mines says Stage 2 dewatering at the Kakula mine, in the Democratic Republic of Congo, started on schedule and that the company will provide an update on the copper production guidance for the Kamoa-Kakula complex for 2026 and 2027 once Stage 2 dewatering activities are more advanced.

The Kakula underground mine was forced to temporarily shut down in May after seismic activity resulted in severe flooding.

Stage 1 dewatering activities, to stabilise and maintain current water levels at the mine, were completed in early June.

Three out of the four Stage 2 high-capacity, submersible pumps were recently installed and commissioned on schedule. Kamoa-Kakula’s engineering team expect to have all four Stage 2 pumps operating within the coming days, operating at a combined pumping rate of about 2 600 ℓ a second.

Since the commissioning of the three Stage 2 pumps, the underground water level in the Kakula mine has dropped vertically by 10 m, out of a total of about 80 m.

Once all four Stage 2 pumps are operational, the existing Stage 1 temporary, underground pumping infrastructure will be repositioned further down the mine, following the water level as it declines.

The total pumping rate out of the Kakula mine is expected to increase up to a target of about 6 400 ℓ a second, or 550 Mℓ a day, reducing the vertical underground water level by about 1 m a day.

The majority of the Stage 2 dewatering is expected to be complete by the end of November.

As the underground water level falls, the underground mining team have already started systematically rehabilitating the newly dewatered areas of the mine. The team is initially focused on rehabilitating the areas required for repositioning the Stage 1 underground pumping infrastructure.

Mine planning and scheduling is well advanced to support the ramp-up of underground mining activities from both Kakula and Kamoa mines, with a medium-term target of returning the copper production rate to over 550 000 t/y.

In the meantime, copper production guidance for 2026 and 2027 will be deferred until sufficient physical inspection of the newly dewatered areas of the Kakula mine has been completed.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Research Reports

Projects

Image of dam
Coerney dam project, South Africa
Updated 2 hours 47 minutes ago By: Sheila Barradas

Latest Multimedia

The above image depicts the helicopter airlifting the HVAC units onto  roof of Bedford Centre
Centre installs new HVAC system
Updated 2 hours 47 minutes ago By: Lynne Davies

Showroom

Hanna Instruments (Pty) Ltd
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 
Actom
Actom

Your one-stop global energy-solution partner

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (12/09/2025)
12th September 2025 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.072 1.019s - 186pq - 2rq
Subscribe Now