KenGen says new geothermal plant nearly ready
KenGen's new 165.4 MW capacity plant powered by geothermal steam is three quarters complete and on schedule for commissioning next July, Kenya's main electricity producer said on Friday.
Geothermal steam, hot underground steam found in the Rift Valley which is used to drive turbines for electricity production, is the second biggest source of Kenya's annual power generation of 2 336 MW, accounting for 26.84% of the total.
Construction of the Olkaria V plant started last year, with contractors including Mitsubishi Corporation.
"Two generator units, each weighing 130 metric tonnes, departed the Port of Mombasa yesterday, signalling the beginning of the final process towards the completion of the plant," the company said in a statement.
KenGen has an installed capacity of 1 631 MW and it plans to add an additional 720 MW by 2020 to cater for growing electricity demand, it said.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation