Nyanzaga gold project advances toward first gold production in 2027

Nyanzaga gold project birds eye view

Nyanzaga gold project

4th February 2026

By: Darren Parker

Deputy Editor Online

     

Font size: - +

Construction at Perseus Mining’s Nyanzaga gold project, in Tanzania, is progressing steadily, with key milestones achieved across operational, mining, and community programmes, the company reported in its first 2026 project update on February 4. The project remains on track to produce its first gold in the first quarter of 2027.

As of mid-January, the operation has recorded nearly four-million workhours with 358 days without a lost-time injury. The first concrete lift on the ball and sag mill has been completed, while installation of the carbon-in-leach tanks continues as planned. Four tanks have reached top strake jacking, and three tanks are progressing with floor plate installation.

Construction of the permanent camp is also advancing, with completion scheduled for mid-2026, providing essential facilities for the workforce. Initial mining preparation has also commenced on the ramp to the top of the Tusker Hill deposit, signalling the start of early extraction activities.

Meanwhile, community and resettlement programmes have moved into their final stages. The resettlement housing programme is completing the last homes, and infrastructure work has begun at schools, a local clinic, and a church. These initiatives are part of the project’s efforts to support local communities alongside mining operations.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Comments

Showroom

Environmental Impact Management Services
Environmental Impact Management Services

EIMS is an independent specialised environmental consulting firm offering the full spectrum of environmental management services across all sectors...

VISIT SHOWROOM 
EKATO Africa
EKATO Africa

Established in 1933, EKATO is the world leader in agitation technology, supplying agitators for processes and applications such as chemicals and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (30/01/2026)
30th January 2026 By: Martin Creamer
Trade, industrial policy decisions loom
Trade, industrial policy decisions loom
30th January 2026 By: Creamer Media Reporter
Magazine cover image
Magazine round up | 30 January 2026
30th January 2026

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.177 0.277s - 189pq - 2rq
Subscribe Now